Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-007Critical4ExecutionConstruction

SCA Academy Campus, Riyadh

Remove from watchlist

A 92,000 m² campus with 42 training halls and practical workshops — ending nine leased training venues and bringing the Academy’s programmes to one site.

Early warning: ⁦97%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 640M

Actual cost

SAR 444.9M

⁦70%⁩ of budget

Progress

⁦57%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 780.5M

SAR +140.5M

SPI · CPI

0.70Schedule performance index · 0.700.82Cost performance index · 0.82

Forecast finish

⁦2027-06-01⁩

152 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure7 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 December 2023Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 February 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate23 July 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate7 October 2026Closure · Not startedClosure · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 640M split into spent, committed and left, with the estimate at completion

Forecast overrun SAR 140.5M
EAC SAR 780.5M
Revised request SAR 640M
  • Actual spendSAR 444.9M
  • Committed, not spentSAR 173.1M
  • Allotted, uncommittedSAR 2.8M
  • Contingency availableSAR 19.2M

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SAR 576M
Original budgetwhen the first baseline was approved
SAR 640M
Approved budgetafter approved change requests
SAR 640M
Current budgetavailable to spend now
SAR 640M
Revised budgetif the pending changes are approved
SAR 640M

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SAR 618M
Contracts2 active contracts
SAR 603.5M
Purchase orders⁦3⁩ orders
SAR 14.5M
Remaining budgetapproved less actual
SAR 195.1M

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SAR 444.9M
Accrualswork done, not yet invoiced
SAR 17.8M
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SAR 780.5M
ContingencySAR 12.8M drawn of SAR 32M
SAR 19.2M

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSAR 576M
ApprovedSAR 640M
Estimate at completionSAR 780.5M
Approved is SAR 64M (⁦11.1%⁩) above the estimate
The estimate at completion is SAR 204.5M (⁦35.5%⁩) above the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2023-11-21⁩ · The gap between estimated and approved comes from the scope update and the change requests approved after the approval gate.

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-51007
  • WBS elements⁦5⁩ elements · P-2026-007.01 …
  • Purchase orders⁦3⁩ synced · ⁦0⁩ manual
  • Invoices & certificates⁦44⁩ posted · ⁦1⁩ in approval
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 12.8M drawn of SAR 32M

  • Covering realised delivery risks⁦2026-08-29⁩SAR 12.8M

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance37.2546.8346.8346.83⁦−9.58⁩
2Design & permits74.5093.6693.6693.66⁦−19.16⁩
3Civil works235.90296.59296.59296.59⁦−60.68⁩
4MEP works186.24124.227.80227.03⁦−40.79⁩
5Handover86.9156.710.00106.78⁦−19.87⁩
Unallocated contingency19.200.000.009.60⁦+9.60⁩
Total640.00618.00444.88780.49⁦−140.49⁩

Budget split

WBS

SAR 640M

Budget

  • Management & governanceSAR 37.2M⁦6%⁩
  • Design & permitsSAR 74.5M⁦12%⁩
  • Civil worksSAR 235.9M⁦37%⁩
  • MEP worksSAR 186.2M⁦29%⁩
  • HandoverSAR 86.9M⁦14%⁩
  • Unallocated contingencySAR 19.2M⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative
  • Forecast

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2029-02-06⁩+768

SPI(t) ⁦0.58⁩ against the approved finish ⁦2026-12-31⁩

Planned valuePV
SAR 634M
The value of the work that should be done by today.
PV
Earned valueEV
SAR 364.8M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 444.9M
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 640M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦−80.08⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−269.17⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
0.82
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.58
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 780.5M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 335.6M
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦−140.49⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
1.41
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 780.5M
  • If the rest goes to planSAR 720.1M
  • At cost and schedule performanceSAR 1B
  • The PM’s bottom-up estimateSAR 780.5M
  • To stay within SAR 640M, cost performance on the rest must rise to ⁦1.41⁩ — above what has been achieved.

Estimate at completion at that performance

SAR 780.5M

Variance at completion: ⁦−140.49⁩ SAR M

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close