Execution
Change request
The change, its impact analysis and the approval decision
- Form no.
- SCA-PMO-F09
- Template edition
- 3.1
- Version
- V1
- Form date
- 2026-10-01
- Hijri
- 20 Rabiʻ II 1448 AH
Auto-filled — Filled by the platform from the project record, not typed.
- Project code
- PRJ-2026-007
- Project
- SCA Academy Campus, Riyadh
- Portfolio
- Academy & Qualification Centres Portfolio
- Sector
- Qualification & Training Sector
- Sponsor
- Eng. Turki A. Al-Anazi
- Project manager
- Eng. Shahad M. Al-Malki
1The change
- TitleAuto-filled
- Extend the contract by 150 days
- KindAuto-filled
- Schedule
- Requested byAuto-filled
- Eng. Shahad M. Al-Malki
- Raised onAuto-filled
- 2026-10-01
Reason
Accumulated façade and MEP delays
Justification
A realistic extension allows an achievable baseline instead of open-ended delay
2Impact analysis
Cost
SAR 0
Schedule
+150 days
Risk
16 → 12
Benefits
-6%
Risk impact
Eases schedule pressure but adds indirect cost
Benefits impact
Academy programmes move in five months later and the training-venue leases run on
3The approval decision
The PMO’s recommendation
The change control board deferred the decision pending the independent engineer’s report
- Change Committee decision
- Not taken yet
- Decided on
- —
- Decision number
- —
Approval logChain: Change request approval · version 5
Every decision on the form — who, their role, the note and the time. It prints with the form.
| # | Step | Kind | Name | Decision | Note | Date & time |
|---|---|---|---|---|---|---|
| 1 | Author | — | Eng. Shahad M. Al-MalkiDirector, Academy Facilities | Submitted | — | 2026-10-01 09:54 |
| 2 | Project manager | Technical acceptance | Eng. Shahad M. Al-MalkiProject manager | Approved | — | 2026-10-04 11:38 |
| 3 | PMO review & impact analysis | Methodology review | Ghada A. Al-ShahraniPMO — analyst | Approved | — | 2026-10-06 12:45 |
| 4 | Change Committee | Technical acceptance | Approval engineChange Committee | Pre-breach alert | — | 2026-10-11 08:00 |
| 5 | Change Committee | Technical acceptance | Approval engineEscalated automatically to Senior management (Dr. Abdullah S. Al-Qahtani) on 2026-10-13 | Automatic escalation | — | 2026-10-13 08:05 |
Signatures
Project manager
Eng. Shahad M. Al-Malki
Approved2026-10-04
PMO review & impact analysis
Ghada A. Al-Shahrani
Approved2026-10-06
Change Committee
Dr. Mohammed I. Al-Subaie
Awaiting decision