Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-007Critical4ExecutionConstruction

SCA Academy Campus, Riyadh

Remove from watchlist

A 92,000 m² campus with 42 training halls and practical workshops — ending nine leased training venues and bringing the Academy’s programmes to one site.

Early warning: ⁦97%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 640M

Actual cost

SAR 444.9M

⁦70%⁩ of budget

Progress

⁦57%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 780.5M

SAR +140.5M

SPI · CPI

0.70Schedule performance index · 0.700.82Cost performance index · 0.82

Forecast finish

⁦2027-06-01⁩

152 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure7 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 December 2023Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 February 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate23 July 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate7 October 2026Closure · Not startedClosure · Not started

Corrective plan

Actions, owners, dates and status

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Corrective plan

Actions, owners, dates and status

Form no.
SCA-PMO-F11
Template edition
1.4
Version
V1
Form date
⁦2026-10-24⁩
Hijri
13 Jumada I 1448 AH
In approvalCP-2026-03Corrective plan — SCA Academy Campus, Riyadh

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-007
Project
SCA Academy Campus, Riyadh
Portfolio
Academy & Qualification Centres Portfolio
Sector
Qualification & Training Sector
Sponsor
Eng. Turki A. Al-Anazi
Project manager
Eng. Shahad M. Al-Malki

1Why the planAuto-filled

Slip when detected

131 days

SPI

0.72

Finish without the plan

⁦2027-07-31⁩

Finish with the plan

⁦2027-06-01⁩

Causes

Unapproved curtain-wall samples, a skilled-labour shortage at the MEP subcontractor, and the pricing dispute over variation 7

2Actions

ActionOwnerDueStatusDays won back
Rule on the façade samples or approve an equivalentEng. Shahad M. Al-Malki⁦2026-10-15⁩In progress25
Require the main contractor to supply replacement MEP labourEng. Abdulrahman S. Al-Harbi⁦2026-11-09⁩Not started15
Prepare the claims file for the dispute boardEng. Shahad M. Al-Malki⁦2026-11-06⁩In progress0
Re-sequence the fit-out to run in parallel in both buildingsEng. Shahad M. Al-Malki⁦2026-11-30⁩Not started20
Total———60

3Support requested

Amount
SAR 0
Detail
A decision to accept an equivalent façade on the consultant’s advice

4PMO follow-upAuto-filled

DateSPISlipNote
No follow-up yet

Approval logChain: Corrective plan approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Shahad M. Al-MalkiDirector, Academy FacilitiesSubmitted—⁦2026-10-24⁩ 12:03
2Programme manager reviewTechnical acceptanceApproval engineProgramme managerPre-breach alert—⁦2026-10-27⁩ 08:00

Signatures

Programme manager review

Dr. Noura M. Al-Otaibi

Awaiting decision

Projects Steering Committee approval

Dr. Abdullah S. Al-Qahtani

Later

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F11 · version V1

Corrective plan

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Corrective plan approval · version ⁦1⁩

Submitted by Eng. Shahad M. Al-Malki on ⁦2026-10-24⁩

  1. Technical acceptance

    Programme manager review

    Dr. Noura M. Al-Otaibi · Programme manager
    1 working day overdueAction time limit exceeded · Limit 3 working daysLimit 3 working days · Due ⁦2026-10-27⁩

    Pre-breach alert at ⁦70%⁩ — sent ⁦2026-10-27⁩

  2. Technical acceptance

    Projects Steering Committee approval

    Dr. Abdullah S. Al-Qahtani · Projects Steering Committee

    Limit 5 working days · Expected by ⁦2026-11-03⁩

Steps that do not apply to this record

  • Financial support requested — the condition «Financial link?» does not hold

Previous versions

Every version is kept with its status and what changed.

  1. V1In approvalCurrent⁦2026-10-24⁩

    The current version

    Eng. Shahad M. Al-Malki

Only one version so far.