CP-2026-03Version 1
SCA Academy Campus, Riyadh
One corrective plan: why the project slipped, the rule that triggered it, the actions, the days won back, approval and follow-up.
What triggered the plan
The project’s reading the day the rule fired, and today.
Detected on 2026-09-01
Slip past the baseline
- At detection
- 131 days
- Today
- 152 days
- Limit
- > 40
Schedule performance index
- At detection
- 0.72
- Today
- 0.70
- Limit
- < 0.85
A rule approved by the Project Approval Committee (PMO-2026/14), read automatically from the project’s data.
Days won back
The forecast finish without the plan, with it, and the difference.
Baseline
2026-12-31Without the plan
2027-07-31+212 days
With the plan
2027-06-01+152 days
Wins back 60 days
Achieved so far: 0 days
Why it slipped
Unapproved curtain-wall samples, a skilled-labour shortage at the MEP subcontractor, and the pricing dispute over variation 7
Corrective actions
Each action with its owner, date, status and the days it wins back; overdue ones are shaded.
Rule on the façade samples or approve an equivalent
Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Academy FacilitiesP-022s.almalki@sca.saACT-0311Overdue13 days overdue2026-10-154 Jumada I 1448 AHWins back 25 daysRequire the main contractor to supply replacement MEP labour
Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDean, SCA AcademyP-014ab.alharbi@sca.saNot startedIn 12 days2026-11-0929 Jumada I 1448 AHWins back 15 daysPrepare the claims file for the dispute board
Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Academy FacilitiesP-022s.almalki@sca.saACT-0310In progressIn 9 days2026-11-0626 Jumada I 1448 AHRe-sequence the fit-out to run in parallel in both buildings
Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Academy FacilitiesP-022s.almalki@sca.saNot startedIn 33 days2026-11-3020 Jumada II 1448 AHWins back 20 days
Follow-up
The project’s readings after the plan was approved, with the PMO’s notes.
No readings yet; follow-up starts after approval.