PRJ-2026-007Critical4ExecutionConstruction

SCA Academy Campus, Riyadh

Remove from watchlist

A 92,000 m² campus with 42 training halls and practical workshops — ending nine leased training venues and bringing the Academy’s programmes to one site.

Early warning: ⁦97%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 640M

Actual cost

SAR 444.9M

⁦70%⁩ of budget

Progress

⁦57%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 780.5M

SAR +140.5M

SPI · CPI

0.70Schedule performance index · 0.700.82Cost performance index · 0.82

Forecast finish

⁦2027-06-01⁩

152 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure7 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 December 2023Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 February 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate23 July 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate7 October 2026Closure · Not startedClosure · Not started

Project charter

Objective, scope, deliverables, roles and budget

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Initiation

Project charter

Objective, scope, deliverables, roles and budget

Form no.
SCA-PMO-F04
Template edition
3.0
Version
V2
Form date
⁦2024-02-02⁩
Hijri
21 Rajab 1445 AH
ApprovedPRJ-2026-007SCA Academy Campus, Riyadh

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-007
Project
SCA Academy Campus, Riyadh
Portfolio
Academy & Qualification Centres Portfolio
Sector
Qualification & Training Sector
Sponsor
Eng. Turki A. Al-Anazi
Project manager
Eng. Shahad M. Al-Malki

1Objective

Background

A 92,000 m² campus with 42 training halls and practical workshops — ending nine leased training venues and bringing the Academy’s programmes to one site.

Project objectives

  1. A sustainable financial base
  2. A better contractor experience and service quality

2Scope

In scope

  • A 92,000 m² campus with 42 training halls and practical workshops — ending nine leased training venues and bringing the Academy’s programmes to one site.
  • Saudi Building Code compliance
  • Consultant-approved drawings

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

3Deliverables and milestones

DeliverableDue
Project management plan⁦2024-03-17⁩
Main deliverable — stage 1⁦2025-07-29⁩
Main deliverable — final stage⁦2026-08-04⁩
Final report⁦2026-12-31⁩
MilestoneDate
Charter approved⁦2024-02-02⁩
Contract signed⁦2024-07-23⁩
50% of works complete⁦2025-07-29⁩
Provisional acceptance⁦2026-10-07⁩
Closure⁦2026-12-31⁩

4RolesAuto-filled

SponsorAuto-filled
Eng. Turki A. Al-Anazi
Project ownerAuto-filled
Eng. Abdulrahman S. Al-Harbi
Project managerAuto-filled
Eng. Shahad M. Al-Malki
StakeholderRole
Project sponsorDecisions and funding
Project ownerAccepts deliverables, owns benefits
Project Management Office (PMO)Governance and compliance
Governance bodyRoleCadence
Change Control BoardApproves scope, cost and schedule changesWeekly
PMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly

5BudgetAuto-filled

LineAmount
Main contractSAR 460.8M
Supervision & consultingSAR 89.6M
Internal teamSAR 57.6M
Contingency reserve (5%)SAR 32M
Approved budgetSAR 640M

Funding

The owning sector’s approved budget

6Success criteria and constraints

Success criteria

  • Delivered within the approved budget
  • On the approved date ±5%
  • Target benefits within 12 months

Constraints

  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

Assumptions

  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

Approval logChain: Project charter approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Shahad M. Al-MalkiDirector, Academy FacilitiesSubmitted—⁦2024-01-24⁩ 10:00
2PMO complianceMethodology reviewDr. Noura M. Al-OtaibiPMO — directorApproved—⁦2024-01-27⁩ 12:30
3Project ownerTechnical acceptanceEng. Abdulrahman S. Al-HarbiProject ownerApproved—⁦2024-01-30⁩ 09:45
4Budget funding confirmedFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2024-01-31⁩ 11:10
5Sponsor approvalTechnical acceptanceEng. Turki A. Al-AnaziProject sponsorApproved—⁦2024-02-02⁩ 11:00

Signatures

PMO compliance

Dr. Noura M. Al-Otaibi

Approved⁦2024-01-27⁩

Project owner

Eng. Abdulrahman S. Al-Harbi

Approved⁦2024-01-30⁩

Budget funding confirmed

Munirah A. Al-Khalidi

Approved⁦2024-01-31⁩

Sponsor approval

Eng. Turki A. Al-Anazi

Approved⁦2024-02-02⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F04 · version V2

Project charter

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project charter approval · version ⁦1⁩

Submitted by Eng. Shahad M. Al-Malki on ⁦2024-01-24⁩

  1. Methodology review

    PMO compliance

    Dr. Noura M. Al-Otaibi · PMO — director

    Approved · ⁦2024-01-27⁩ at ⁦12:30⁩

  2. Technical acceptance

    Project owner

    Eng. Abdulrahman S. Al-Harbi · Project owner

    Approved · ⁦2024-01-30⁩ at ⁦09:45⁩

  3. Financial approval

    Budget funding confirmed

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2024-01-31⁩ at ⁦11:10⁩

  4. Technical acceptance

    Sponsor approval

    Eng. Turki A. Al-Anazi · Project sponsor

    Approved · ⁦2024-02-02⁩ at ⁦11:00⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2024-02-02⁩

    Approved version

    • PMO comments addressed

    Eng. Shahad M. Al-Malki

  2. V1Returned for edit⁦2024-01-14⁩

    First draft

    • Returned to detail the budget

    Eng. Shahad M. Al-Malki

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close