Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-007Critical4ExecutionConstruction

SCA Academy Campus, Riyadh

Remove from watchlist

A 92,000 m² campus with 42 training halls and practical workshops — ending nine leased training venues and bringing the Academy’s programmes to one site.

Early warning: ⁦97%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 640M

Actual cost

SAR 444.9M

⁦70%⁩ of budget

Progress

⁦57%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 780.5M

SAR +140.5M

SPI · CPI

0.70Schedule performance index · 0.700.82Cost performance index · 0.82

Forecast finish

⁦2027-06-01⁩

152 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure7 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 December 2023Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 February 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate23 July 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate7 October 2026Closure · Not startedClosure · Not started

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Form no.
SCA-PMO-F08
Template edition
1.1
Version
V1
Form date
⁦2025-09-29⁩
Hijri
7 Rabiʻ II 1447 AH
ApprovedCRT-007-04Permits & approvals

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-007
Project
SCA Academy Campus, Riyadh
Portfolio
Academy & Qualification Centres Portfolio
Sector
Qualification & Training Sector
Sponsor
Eng. Turki A. Al-Anazi
Project manager
Eng. Shahad M. Al-Malki

1The deliverableAuto-filled

DeliverableAuto-filled
Permits & approvals
DescriptionAuto-filled
A contractual output tied to its WBS work package.
OwnerAuto-filled
Eng. Turki A. Al-Anazi
VersionAuto-filled
V1
Weight in the projectAuto-filled
⁦6%⁩
DueAuto-filled
⁦2025-02-25⁩

2Evidence of completionAuto-filled

FileVersionByDate
PRJ-2026-007_2.2_v1.pdfV1Eng. Turki A. Al-Anazi⁦2025-03-04⁩

3Inspection and acceptance criteria

CriterionResult
Matches the approved scope of workMet
Quality review with no major findingsMet
Evidence attached and signed by the ownerMet
Met3 of 3
InspectorAuto-filled
Eng. Abdulrahman S. Al-Harbi
Accepted byAuto-filled
Eng. Turki A. Al-Anazi
Acceptance note
Inspected and accepted against the approved acceptance criteria.

4Financial linkAuto-filled

Contract milestoneAuto-filled
Designs approved
ContractAuto-filled
CTR-2024-006
Payment certificateAuto-filled
Linked when the certificate is raised
Payment against itAuto-filled
—

Approval logChain: Deliverable acceptance & certificate · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Turki A. Al-AnaziHead, Qualification & Training SectorSubmitted—⁦2025-03-04⁩ 14:23
2Evidence against the acceptance criteriaMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-03-06⁩ 14:17
3Inspection & technical acceptance — ownerTechnical acceptanceEng. Turki A. Al-AnaziProject ownerOn behalf of Eng. Abdulrahman S. Al-HarbiApprovedInspected and accepted against the approved acceptance criteria.⁦2025-03-09⁩ 09:24
4Deliverable matched to the contract lineFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2025-03-10⁩ 09:54
5Certificate linked to the payment certificateFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2025-03-12⁩ 10:31

Signatures

Evidence against the acceptance criteria

Ghada A. Al-Shahrani

Approved⁦2025-03-06⁩

Inspection & technical acceptance — owner

Eng. Turki A. Al-Anazi

Approved⁦2025-03-09⁩

Deliverable matched to the contract line

Mazen A. Al-Hazmi

Approved⁦2025-03-10⁩

Certificate linked to the payment certificate

Munirah A. Al-Khalidi

Approved⁦2025-03-12⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F08 · version V1

Deliverable completion certificate

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Deliverable acceptance & certificate · version ⁦1⁩

Submitted by Eng. Turki A. Al-Anazi on ⁦2025-03-04⁩

  1. Methodology review

    Evidence against the acceptance criteria

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-03-06⁩ at ⁦14:17⁩

  2. Technical acceptance

    Inspection & technical acceptance — owner

    Eng. Abdulrahman S. Al-Harbi · Project owner

    Approved · ⁦2025-03-09⁩ at ⁦09:24⁩ · On behalf of Eng. Abdulrahman S. Al-Harbi (Eng. Turki A. Al-Anazi)

    Inspected and accepted against the approved acceptance criteria.

  3. Financial approval

    Deliverable matched to the contract line

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2025-03-10⁩ at ⁦09:54⁩

  4. Financial approval

    Certificate linked to the payment certificate

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2025-03-12⁩ at ⁦10:31⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2025-03-04⁩

    PRJ-2026-007_2.2_v1.pdf

    Eng. Turki A. Al-Anazi

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close