Contractor claims file — SCA Academy campus
SCA Academy Campus, Riyadh
The parties
This contract is made between the Saudi Contractors Authority (first party) and the contractor named in the data sheet (second party), under the Government Tenders and Procurement Law and its regulations.
- Project
- SCA Academy Campus, Riyadh (PRJ-2026-007)
- Project manager
- Eng. Shahad M. Al-Malki
- Budget
- SAR 640.0M
- Progress
- 57% actual against 82% planned
- Forecast finish
- 2027-06-01
Key terms
- Delay penalty 0.5% a week, capped at 10% of the contract value
- A 5% performance bond valid until final handover
- 10% retention on every certificate
Addendum 1
This addendum amends the payment schedule and adds complementary works within 10% of the contract value.