Saudi Contractors AuthorityMunjaz11My actionsNotifications

Contractor claims file — SCA Academy campus

RestrictedIn reviewV2Checked out to Eng. Shahad M. Al-MalkiLegal hold

The contractor’s claims for variations and extension of time, with technical and legal responses.

More
Showing version:

Restricted

Kingdom of Saudi Arabia

Saudi Contractors Authority

Project Management Office (PMO)

Code
DOC-0213
Version
V2
Date
2026-10-24

Contractor claims file — SCA Academy campus

SCA Academy Campus, Riyadh

The parties

This contract is made between the Saudi Contractors Authority (first party) and the contractor named in the data sheet (second party), under the Government Tenders and Procurement Law and its regulations.

Project
SCA Academy Campus, Riyadh (⁦PRJ-2026-007⁩)
Project manager
Eng. Shahad M. Al-Malki
Budget
SAR ⁦640.0M⁩
Progress
⁦57%⁩ actual against ⁦82%⁩ planned
Forecast finish
⁦2027-06-01⁩

Key terms

  • Delay penalty ⁦0.5%⁩ a week, capped at ⁦10%⁩ of the contract value
  • A ⁦5%⁩ performance bond valid until final handover
  • ⁦10%⁩ retention on every certificate

Addendum ⁦1⁩

This addendum amends the payment schedule and adds complementary works within ⁦10%⁩ of the contract value.

Prepared by

Eng. Shahad M. Al-Malki
Issued from Munjaz — valid only once approved electronically1 / 1

Restricted

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close