RSK-0024Jeddah Branch & Qualification Centre

Ground-improvement costs up after the geotechnical survey

16HighEscalatedMaterial

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

The geotechnical survey found softer soil and higher groundwater than the design study assumed

Preventive controls

  • A change request for the extra ground improvement
  • Value engineering of the foundation solution with the consultant

1 / 2

Event

Ground-improvement costs up after the geotechnical survey

16HighTrigger

The change request is not approved at the next CCB meeting

Contingency

Treat the ground in two stages, the training & test hall block first

Impact

SAR 22.5M of extra ground improvement and a 75-day extension

SAR 22.5M

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
16High

Residual

5
4
3
2
1
1
2
3
4
5
6Low

Exposure

SAR 22.5M

Residual

⁦63⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director

Last reviewed 6 days ago

  1. Project manager

    Eng. Fahad T. Al-Sulami

    Currently followed up here
  2. Programme manager

    Current level

    Eng. Fahad T. Al-Sulami

    Automatically at 15 days unreviewed · in 9 days
  3. 3

    PMO director

    Dr. Noura M. Al-Otaibi

    Automatically at 20 days unreviewed · in 14 days
  4. 4

    Executive committee

    Dr. Abdullah S. Al-Qahtani

    By the PMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦1⁩ of ⁦2⁩ done
  • A change request for the extra ground improvement

    Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Regional Qualification CentresP-023f.alsulami@sca.sa
    Done⁦2026-10-06⁩2026-10-0625 Rabiʻ II 1448 AH
  • Value engineering of the foundation solution with the consultant

    Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Regional Qualification CentresP-023f.alsulami@sca.sa
    In progressIn 15 days2026-11-122 Jumada II 1448 AH

Trigger

The change request is not approved at the next CCB meeting

Contingency

Treat the ground in two stages, the training & test hall block first

Esc