PRJ-2026-006Off track4ExecutionConstruction

Jeddah Branch & Qualification Centre

Remove from watchlist

A new home for the Western & Southern branch in Jeddah with a qualification centre of 40 training and skills-test halls and contractor service desks.

Early warning: ⁦84%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 286M

Actual cost

SAR 125.3M

⁦44%⁩ of budget

Progress

⁦39%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 321.3M

SAR +35.3M

SPI · CPI

0.78Schedule performance index · 0.780.89Cost performance index · 0.89

Forecast finish

⁦2027-07-04⁩

95 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate30 January 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 January 2027Closure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−21

May to October 2026

No material change in the health dimensions over the period.

AI insight

⁦84%⁩ chance of a further slip within ⁦45⁩ days

From the SPI trend (⁦0.78⁩), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.

Confidence⁦82%⁩

Copilot summary

Generated from the live project data

The project is behind plan: ⁦39%⁩ done against ⁦50%⁩ planned.

SPI ⁦0.78⁩, CPI ⁦0.89⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: Specialised, Value-adding ServicesSO-3.3A better contractor experience and service quality

Main initiative

SI-3.1.1Branches & regional centres

Contribution to the initiative⁦64%⁩

The project’s share of the initiative’s project budget (2 projects)

Secondary links

Annual work-plan line
WP-2024-006
Classification
Strategic

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦39%⁩

Awaiting acceptance ⁦11%⁩

Not handed in ⁦50%⁩

5 deliverables accepted

  • Site works & excavation⁦16%⁩
  • Detailed design⁦8%⁩
  • Permits & approvals⁦7%⁩
  • Project plan & baseline⁦4%⁩
  • Monitoring & reporting⁦4%⁩

1 deliverable under inspection or acceptance

  • Structure⁦11%⁩

Corrective plan requiredThe project is seriously late (95 days late · SPI ⁦0.78⁩) and has no corrective plan yet.

Progress & earned value

⁦3⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦89%⁩ of budget

125.3M/ 286M35.3Mprojected overrun(⁦12.4%⁩)
Actual spend
125.3M
Committed
254M
Approved budget
286M
Estimate at completion
321.3M

Next milestones

  • Provisional acceptance⁦2027-03-27⁩was ⁦2027-01-15⁩Late
  • Closure⁦2027-07-04⁩was ⁦2027-03-31⁩Late

Waiting on someone

⁦0⁩ approvals and ⁦1⁩ open action on this project

Approvals & requests

From «My actions» for this project

  • No approvals pending

Actions

⁦1⁩ open

  • Chase the building permits with the Jeddah municipalityEng. Fahad T. Al-SulamiIn 6 days2026-11-0323 Jumada I 1448 AHHigh

Risks & impediments

2 open risks, exposure SAR 28.5M

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩1Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩RSK-0025Late building permits from the Jeddah municipality1Probability: Likely · Impact: MajorHigh · Score ⁦16⁩RSK-0024Ground-improvement costs up after the geotechnical surveyProbability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High1
  • Medium1
  • Low0

Deliverables

⁦5⁩ of ⁦12⁩ approved

  • Project plan & baseline006-D1 · V1 · CRT-006-01⁦4%⁩Eng. Fahad T. Al-Sulami⁦2024-12-29⁩2024-12-2928 Jumada II 1446 AHApproved
  • Monitoring & reporting006-D2 · V1 · CRT-006-02⁦4%⁩Eng. Abdulrahman S. Al-Harbi⁦2025-03-14⁩2025-03-1414 Ramadan 1446 AHApproved
  • Detailed design006-D3 · V1 · CRT-006-03⁦8%⁩Eng. Abdulrahman S. Al-Harbi⁦2025-05-28⁩2025-05-281 Dhuʻl-Hijjah 1446 AHApproved
  • Permits & approvals006-D4 · V1 · CRT-006-04⁦7%⁩Eng. Turki A. Al-Anazi⁦2025-08-11⁩2025-08-1117 Safar 1447 AHApproved
  • Site works & excavation006-D5 · V1 · CRT-006-05⁦16%⁩Eng. Turki A. Al-Anazi⁦2025-10-24⁩2025-10-242 Jumada I 1447 AHApproved
  • Structure006-D6 · V1⁦11%⁩Eng. Fahad T. Al-Sulami294 days overdue2026-01-0718 Rajab 1447 AHIn review
  • Finishes006-D7 · V0⁦11%⁩Eng. Abdulrahman S. Al-Harbi219 days overdue2026-03-234 Shawwal 1447 AHDraft
  • Supply006-D8 · V0⁦9%⁩Eng. Fahad T. Al-Sulami145 days overdue2026-06-0519 Dhuʻl-Hijjah 1447 AHDraft
  • Installation006-D9 · V0⁦9%⁩Eng. Abdulrahman S. Al-Harbi70 days overdue2026-08-196 Rabiʻ I 1448 AHDraft
  • Testing & commissioning006-D10 · V0⁦9%⁩Eng. Turki A. Al-AnaziIn 5 days2026-11-0222 Jumada I 1448 AHDraft
  • Provisional acceptance006-D11 · V0⁦6%⁩Eng. Abdulrahman S. Al-HarbiIn 79 days2027-01-157 Shaʻban 1448 AHDraft
  • Final acceptance006-D12 · V0⁦6%⁩Eng. Turki A. Al-AnaziIn 154 days2027-03-3123 Shawwal 1448 AHDraft

Team, contracts & documents

Team

2 members

Eng. Fahad T. Al-Sulami · Director, Regional Qualification CentresEng. Abdulrahman S. Al-Harbi · Dean, SCA Academy
  • Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Regional Qualification CentresProject managerP-023f.alsulami@sca.sa⁦55%⁩
  • Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDean, SCA AcademyProject sponsorP-014ab.alharbi@sca.sa⁦25%⁩
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close