PRJ-2026-006Off track4ExecutionConstruction
Jeddah Branch & Qualification Centre
Remove from watchlistA new home for the Western & Southern branch in Jeddah with a qualification centre of 40 training and skills-test halls and contractor service desks.
Project managerEng. Fahad T. Al-SulamiProject sponsorEng. Turki A. Al-AnaziProgrammeBranches & Regional Centres Programme
Early warning: 84% chance of slipping within 45 days
Budget (BAC)
SAR 286M
Actual cost
SAR 125.3M
44% of budget
Progress
39%Awaiting acceptance 11%
Estimate at completion
SAR 321.3M
SAR +35.3M
SPI · CPI
0.78Schedule performance index · 0.780.89Cost performance index · 0.89
Forecast finish
2027-07-04
95 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure15 January 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate30 January 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate15 January 2027Closure · Not startedClosure · Not started