Jeddah Branch & Qualification Centre
Remove from watchlistA new home for the Western & Southern branch in Jeddah with a qualification centre of 40 training and skills-test halls and contractor service desks.
Budget (BAC)
Actual cost
44% of budget
Progress
Estimate at completion
SAR +35.3M
SPI · CPI
Forecast finish
95 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure15 January 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate30 January 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate15 January 2027Closure · Not startedClosure · Not started
Team & roles
2 members, about 0.8 full-time equivalents
Leadership
2 members
- Eng. Fahad T. Al-SulamiProject manager55%A
- Eng. Abdulrahman S. Al-HarbiProject sponsor25%Allocated 110% across all projectsR
A AccountableR ResponsibleC ConsultedI Informed
Stakeholders
6 stakeholders, 4 of them below the engagement needed
Power / interest matrix
Pick one to see how they are handled
Keep satisfied1
high power, lower interest
Manage closely4
high power and interest
Monitor0
minimal effort
Keep informed1
high interest, lower power
Interest
Project sponsor
Eng. Turki A. Al-Anazi
Decisions and funding
Influence
Interest
Engagement level
Unaware
Resistant
Neutral
Supportive
Leading
A gap of 1 step — needs an engagement plan.
- Impact on the project
- Approves gates and changes
- Engagement plan
- Monthly briefing
Display options
| Organisation | Role | Actions | ||||||
|---|---|---|---|---|---|---|---|---|
| Eng. Turki A. Al-Anazi | Project sponsor | Decisions and funding | SupportiveLeading | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Regional Qualification CentresP-023f.alsulami@sca.sa | 2026-10-17 | |||
| Eng. Abdulrahman S. Al-Harbi | Project owner | Accepts deliverables, owns benefits | ResistantLeading | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Regional Qualification CentresP-023f.alsulami@sca.sa | 2026-10-20 | |||
| Project Management Office (PMO) | Governance | Compliance and data quality | Supportive | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Regional Qualification CentresP-023f.alsulami@sca.sa | 2026-10-14 | |||
| General Directorate of Financial Affairs | Internal department | Payment approval | NeutralSupportive | Haifa S. Al-RuwailiHaifa S. Al-RuwailiSenior Financial AnalystP-037h.alruwaili@sca.sa | 2026-10-11 | |||
| Bait Al-Khebra Engineering Consultants | Main vendor | Delivers the contracted work | Supportive | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Regional Qualification CentresP-023f.alsulami@sca.sa | 2026-10-21 | |||
| End beneficiaries | Beneficiaries | Users of the outcome | NeutralSupportive | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Regional Qualification CentresP-023f.alsulami@sca.sa | 2026-09-23 |
Communication plan
Who needs what, when, through which channel, and who owns it.
- Project sponsorStatus and decisions neededMonthlyMeetingEng. Fahad T. Al-Sulami2026-11-12
- Project ownerDeliverable status and acceptance datesFortnightlyEmailEng. Fahad T. Al-Sulami2026-10-31
- PMOData and indicator updatesWeeklyDashboardEng. Fahad T. Al-Sulami2026-10-28
- BeneficiariesWhat changes and whenAt milestonesNewsletterEng. Fahad T. Al-SulamiAt launch
Coming up
By date
- 282026-10PMODashboard · Weekly
- 312026-10Project ownerEmail · Fortnightly
- 122026-11Project sponsorMeeting · Monthly