Original
Original baseline
- Finish
- 2027-03-31
- Budget
- SAR 276.4M
- 17 activities
Approved with the project plan at the planning gate.
Approved 2024-09-01 · by Eng. Turki A. Al-Anazi
A new home for the Western & Southern branch in Jeddah with a qualification centre of 40 training and skills-test halls and contractor service desks.
Budget (BAC)
Actual cost
44% of budget
Progress
Estimate at completion
SAR +35.3M
SPI · CPI
Forecast finish
95 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure15 January 2027
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved with the project plan at the planning gate.
Approved 2024-09-01 · by Eng. Turki A. Al-Anazi
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Eng. Fahad T. Al-Sulami
What changed from version A to version B
Finish
2027-03-312027-06-30
+91 days
Budget
SAR 276.4MSAR 308.5M
+32.10 SAR M
Milestones moved
5 / 5
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SAR millions from A to B
Every saved version with its reason and reference