Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-006Off track4ExecutionConstruction

Jeddah Branch & Qualification Centre

Remove from watchlist

A new home for the Western & Southern branch in Jeddah with a qualification centre of 40 training and skills-test halls and contractor service desks.

Early warning: ⁦84%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 286M

Actual cost

SAR 125.3M

⁦44%⁩ of budget

Progress

⁦39%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 321.3M

SAR +35.3M

SPI · CPI

0.78Schedule performance index · 0.780.89Cost performance index · 0.89

Forecast finish

⁦2027-07-04⁩

95 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate30 January 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 January 2027Closure · Not startedClosure · Not started
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close