PRJ-2026-006Off track4ExecutionConstruction
Jeddah Branch & Qualification Centre
Remove from watchlistA new home for the Western & Southern branch in Jeddah with a qualification centre of 40 training and skills-test halls and contractor service desks.
Project managerEng. Fahad T. Al-SulamiProject sponsorEng. Turki A. Al-AnaziProgrammeBranches & Regional Centres Programme
Early warning: 84% chance of slipping within 45 days
Budget (BAC)
SAR 286M
Actual cost
SAR 125.3M
44% of budget
Progress
39%Awaiting acceptance 11%
Estimate at completion
SAR 321.3M
SAR +35.3M
SPI · CPI
0.78Schedule performance index · 0.780.89Cost performance index · 0.89
Forecast finish
2027-07-04
95 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure15 January 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate30 January 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate15 January 2027Closure · Not startedClosure · Not started
Periodic update cards
Filled by the project manager every period — progress, status, risks and support requested — prefilled from the previous card and the live data, then approved.
Period
October 2026
In approvalDue todayAction time limit about to lapse · Limit 2 working days
- Progress
- 39%
- Planned
- 50%
- SPI
- 0.78
Periodic update cards
| Period | Status | Progress | Current step | Date |
|---|---|---|---|---|
| October 2026UPD-006-2026-10 | In approval | 39% | Methodology reviewDr. Noura M. Al-OtaibiDue todayAction time limit about to lapse · Limit 2 working days | 2026-10-26 |
| September 2026UPD-006-2026-09 | Approved | 37% | — | 2026-10-02 |
| August 2026UPD-006-2026-08 | Approved | 35% | — | 2026-09-02 |