Jeddah Branch & Qualification Centre
Remove from watchlistA new home for the Western & Southern branch in Jeddah with a qualification centre of 40 training and skills-test halls and contractor service desks.
Budget (BAC)
Actual cost
44% of budget
Progress
Estimate at completion
SAR +35.3M
SPI · CPI
Forecast finish
95 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure15 January 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate30 January 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate15 January 2027Closure · Not startedClosure · Not started
Project lifecycle and its gates
Current phase: Execution. Pick a gate on the track to review it.
- Gate into «Initiation»DecisionConditional goDate3 July 2024Mandatory criteria met, with points to close during the next phase.Pre-startComplete
- Gate into «Planning»DecisionGoDate1 September 2024All criteria and required documents met.InitiationComplete
- Gate into «Execution»DecisionGoDate30 January 2025All criteria and required documents met.PlanningComplete
- Gate into «Closure»DecisionNot held yetDate15 January 2027ExecutionCurrent stageCurrent stage
- 5ClosureNot started
What each stage requires
The documents and approvals each gate asks for before the next stage.
Closure gate — deliverables accepted and handed over
Gate readiness
Enough for a conditional go only
Automated control: no move until the criteria are met
- 3 mandatory checklist items open
- 1 required document not approved
- 2 mandatory criteria under 70 points
- Weighted score 66 under the pass mark 75
Checklist
4 of 7 done
- Deliverable completion certificates approved for every deliverableMandatory
- Acceptance tests and handover to operations completeMandatory
- Open commitments listed with a plan to close themMandatory
- Deliverable-linked payments settledMandatory
- Pilot run with no critical or high findingsMandatory
- Users trained
- Launch rollback plan
Required documents
3 of 4 approved
- Deliverable completion certificatesApproved · V1
- Project closure & handover formApproved · V1
- Lessons-learned logSubmitted — awaiting acceptance · V1
- Benefits measurement planApproved · V1
Criteria and score
Go from 75, conditional from 60; a mandatory criterion is met from 70.
Deliverables acceptedweight 35%Not met
Awaiting evidence from the project team.
Quality & securityweight 25%Not met
Awaiting evidence from the project team.
Operations & handover readinessweight 25%Met
Awaiting evidence from the project team.
User & training readinessweight 15%
Awaiting evidence from the project team.
Approvers
Project Management Office
- Dr. Noura M. Al-OtaibiPMO directorVote pending
- Eng. Abdulrahman S. Al-HarbiProject ownerVote pending
- Eng. Turki A. Al-AnaziProject sponsorVote pending