Jeddah Branch & Qualification Centre
Remove from watchlistA new home for the Western & Southern branch in Jeddah with a qualification centre of 40 training and skills-test halls and contractor service desks.
Budget (BAC)
Actual cost
44% of budget
Progress
Estimate at completion
SAR +35.3M
SPI · CPI
Forecast finish
95 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure15 January 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate30 January 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate15 January 2027Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-03-14 | 2025-09-02 | +172 days | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Regional Qualification CentresP-023f.alsulami@sca.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-08-11 | 2026-06-10 | +303 days | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Regional Qualification CentresP-023f.alsulami@sca.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-03-23 | 2027-01-11 | +294 days | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Regional Qualification CentresP-023f.alsulami@sca.sa | Late | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-11-02 | 2027-04-23 | +172 days | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Regional Qualification CentresP-023f.alsulami@sca.sa | At risk | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2027-03-31 | 2027-06-30 | +91 days | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Regional Qualification CentresP-023f.alsulami@sca.sa | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
39%Awaiting acceptance
11%Not handed in
50%Deliverable flow
Display options
| Project plan & baseline006-D1 | 4% | CRT-006-01 | Approved | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Regional Qualification CentresP-023f.alsulami@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2024-12-29 | V1 | 3 of 3 |
| Monitoring & reporting006-D2 | 4% | CRT-006-02 | Approved | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDean, SCA AcademyP-014ab.alharbi@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2025-03-14 | V1 | 3 of 3 |
| Detailed design006-D3 | 8% | CRT-006-03 | Approved | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDean, SCA AcademyP-014ab.alharbi@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2025-05-28 | V1 | 3 of 3 |
| Permits & approvals006-D4 | 7% | CRT-006-04 | Approved | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2025-08-11 | V1 | 3 of 3 |
| Site works & excavation006-D5 | 16% | CRT-006-05 | Approved | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2025-10-24 | V1 | 3 of 3 |
| Structure006-D6 | 11% | — | Under review | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Regional Qualification CentresP-023f.alsulami@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2026-01-07 | V1 | 1 of 3 |
| Finishes006-D7 | 11% | — | Draft | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDean, SCA AcademyP-014ab.alharbi@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2026-03-23 | V0 | 0 of 3 |
| Supply006-D8 | 9% | — | Draft | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Regional Qualification CentresP-023f.alsulami@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2026-06-05 | V0 | 0 of 3 |
| Installation006-D9 | 9% | — | Draft | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDean, SCA AcademyP-014ab.alharbi@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2026-08-19 | V0 | 0 of 3 |
| Testing & commissioning006-D10 | 9% | — | Draft | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2026-11-02 | V0 | 0 of 3 |
| Provisional acceptance006-D11 | 6% | — | Draft | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDean, SCA AcademyP-014ab.alharbi@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2027-01-15 | V0 | 0 of 3 |
| Final acceptance006-D12 | 6% | — | Draft | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2027-03-31 | V0 | 0 of 3 |
| Total · 12 | 100% |