Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-006Off track4ExecutionConstruction

Jeddah Branch & Qualification Centre

Remove from watchlist

A new home for the Western & Southern branch in Jeddah with a qualification centre of 40 training and skills-test halls and contractor service desks.

Early warning: ⁦84%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 286M

Actual cost

SAR 125.3M

⁦44%⁩ of budget

Progress

⁦39%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 321.3M

SAR +35.3M

SPI · CPI

0.78Schedule performance index · 0.780.89Cost performance index · 0.89

Forecast finish

⁦2027-07-04⁩

95 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate30 January 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 January 2027Closure · Not startedClosure · Not started

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Form no.
SCA-PMO-F08
Template edition
1.1
Version
V1
Form date
⁦2025-04-14⁩
Hijri
16 Shawwal 1446 AH
ApprovedCRT-006-01Project plan & baseline

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-006
Project
Jeddah Branch & Qualification Centre
Portfolio
Academy & Qualification Centres Portfolio
Sector
Qualification & Training Sector
Sponsor
Eng. Turki A. Al-Anazi
Project manager
Eng. Fahad T. Al-Sulami

1The deliverableAuto-filled

DeliverableAuto-filled
Project plan & baseline
DescriptionAuto-filled
A contractual output tied to its WBS work package.
OwnerAuto-filled
Eng. Fahad T. Al-Sulami
VersionAuto-filled
V1
Weight in the projectAuto-filled
⁦4%⁩
DueAuto-filled
⁦2024-12-29⁩

2Evidence of completionAuto-filled

FileVersionByDate
PRJ-2026-006_1.1_v1.pdfV1Eng. Fahad T. Al-Sulami⁦2024-09-01⁩

3Inspection and acceptance criteria

CriterionResult
Matches the approved scope of workMet
Quality review with no major findingsMet
Evidence attached and signed by the ownerMet
Met3 of 3
InspectorAuto-filled
Eng. Abdulrahman S. Al-Harbi
Accepted byAuto-filled
Eng. Turki A. Al-Anazi
Acceptance note
Inspected and accepted against the approved acceptance criteria.

4Financial linkAuto-filled

Contract milestoneAuto-filled
Project plan approved
ContractAuto-filled
CTR-2024-019
Payment certificateAuto-filled
Linked when the certificate is raised
Payment against itAuto-filled
—

Approval logChain: Deliverable acceptance & certificate · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Fahad T. Al-SulamiDirector, Regional Qualification CentresSubmitted—⁦2024-09-01⁩ 10:25
2Evidence against the acceptance criteriaMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2024-09-03⁩ 10:19
3Inspection & technical acceptance — ownerTechnical acceptanceEng. Turki A. Al-AnaziProject ownerOn behalf of Eng. Abdulrahman S. Al-HarbiApprovedInspected and accepted against the approved acceptance criteria.⁦2024-09-08⁩ 11:26
4Deliverable matched to the contract lineFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2024-09-09⁩ 09:00
5Certificate linked to the payment certificateFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2024-09-11⁩ 10:37

Signatures

Evidence against the acceptance criteria

Ghada A. Al-Shahrani

Approved⁦2024-09-03⁩

Inspection & technical acceptance — owner

Eng. Turki A. Al-Anazi

Approved⁦2024-09-08⁩

Deliverable matched to the contract line

Mazen A. Al-Hazmi

Approved⁦2024-09-09⁩

Certificate linked to the payment certificate

Munirah A. Al-Khalidi

Approved⁦2024-09-11⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F08 · version V1

Deliverable completion certificate

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Deliverable acceptance & certificate · version ⁦1⁩

Submitted by Eng. Fahad T. Al-Sulami on ⁦2024-09-01⁩

  1. Methodology review

    Evidence against the acceptance criteria

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2024-09-03⁩ at ⁦10:19⁩

  2. Technical acceptance

    Inspection & technical acceptance — owner

    Eng. Abdulrahman S. Al-Harbi · Project owner

    Approved · ⁦2024-09-08⁩ at ⁦11:26⁩ · On behalf of Eng. Abdulrahman S. Al-Harbi (Eng. Turki A. Al-Anazi)

    Inspected and accepted against the approved acceptance criteria.

  3. Financial approval

    Deliverable matched to the contract line

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2024-09-09⁩ at ⁦09:00⁩

  4. Financial approval

    Certificate linked to the payment certificate

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2024-09-11⁩ at ⁦10:37⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2024-09-01⁩

    PRJ-2026-006_1.1_v1.pdf

    Eng. Fahad T. Al-Sulami

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close