PRJ-2026-006
Jeddah Branch & Qualification CentrePlanned to date 50%
- SPI
- 0.78
- Forecast finish
- 2027-07-04
- Budget
- SAR 286M
95 days lateMaterial risks: 1Open impediments: 2Corrective plan required
Ruling on the Jeddah branch & centre contractor’s replacement bank guarantee.
Held on
27 October 202610:00 – 10:50
45 of 60 min
Replacement bank guarantee — Jeddah branch & centre
DecisionMazen A. Al-Hazmi
35 min
Any other business
DiscussionMunirah A. Al-Khalidi
10 min
1. Replacement bank guarantee — Jeddah branch & centre
PRJ-2026-006Accepted on condition its validity is extended; one reservation.
2. Any other business
No minutes were written for this item.
Voting rule: Simple majority; reservations recorded in the minutes
Replacement bank guarantee for the Jeddah branch contractor accepted
DEC-2026-043Approved
For 4Against 1Abstain 0Carried
Ibrahim Al-Ghamdi reserved on the replacement guarantee’s validity period.
They show in the task register and on the owner’s calendar
No tasks from this meeting yet
Quorum: Three of five members, including the chair and a technical member
At least 3 voting members needed
1 file
Drafted by the assistant from the agenda, the minutes, the decisions and the tasks. Review it before approval.
Shown only to invitees and the PMO, and leaves out what your permissions do not let you see.
Built automatically from the projects on the agenda: a card per project, the decisions needed, the support requested and the overdue tasks.
PRJ-2026-006
Jeddah Branch & Qualification CentrePlanned to date 50%
95 days lateMaterial risks: 1Open impediments: 2Corrective plan required
Agenda item needing a decision · PRJ-2026-006
Replacement bank guarantee — Jeddah branch & centreFrom item 1
ISS-0121 · Jeddah Branch & Qualification Centre
An approval· Asked from: Eng. Turki A. Al-Anazi
A sector-head letter to the Jeddah municipality to speed up the permits
Nothing