Wadi Al-Dawasir Vocational Qualification Centre
Add to watchlistA permanent training and skills-test centre for the south of the Riyadh region, waiting for the land handover and title deed.
Budget (BAC)
Actual cost
2% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
184 days behind baseline
PlanningStage 3 of 5
Next gate:Execution15 July 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate31 December 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate1 March 2026Planning · Current stagePlanning · Current stage
- Gate into «Execution»DecisionNot held yetDate15 July 2026Execution · Not startedExecution · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2026-08-24 | 2027-02-15 | +175 days | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Academy FacilitiesP-022s.almalki@sca.sa | Late | 0 | Not requested |
| Designs approvedMS-G2 | Project | 2027-01-06 | 2027-07-03 | +178 days | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Academy FacilitiesP-022s.almalki@sca.sa | At risk | 0 | Not requested |
| Build completeMS-G3 | Contractual | 2027-07-28 | 2028-01-26 | +182 days | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Academy FacilitiesP-022s.almalki@sca.sa | At risk | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2028-02-16 | 2028-08-20 | +186 days | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Academy FacilitiesP-022s.almalki@sca.sa | At risk | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2028-06-30 | 2029-01-05 | +189 days | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Academy FacilitiesP-022s.almalki@sca.sa | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
2%Awaiting acceptance
0%Not handed in
98%Deliverable flow
Display options
| Project plan & baseline033-D1 | 2% | CRT-033-01 | Approved | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Academy FacilitiesP-022s.almalki@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2026-06-17 | V1 | 3 of 3 |
| Monitoring & reporting033-D2 | 3% | — | Draft | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDean, SCA AcademyP-014ab.alharbi@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2026-08-24 | V0 | 0 of 3 |
| Detailed design033-D3 | 6% | — | Draft | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDean, SCA AcademyP-014ab.alharbi@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2026-10-30 | V0 | 0 of 3 |
| Permits & approvals033-D4 | 6% | — | Draft | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2027-01-06 | V0 | 0 of 3 |
| Site works & excavation033-D5 | 13% | — | Draft | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2027-03-15 | V0 | 0 of 3 |
| Structure033-D6 | 13% | — | Draft | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Academy FacilitiesP-022s.almalki@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2027-05-21 | V0 | 0 of 3 |
| Finishes033-D7 | 13% | — | Draft | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDean, SCA AcademyP-014ab.alharbi@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2027-07-28 | V0 | 0 of 3 |
| Supply033-D8 | 10% | — | Draft | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Academy FacilitiesP-022s.almalki@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2027-10-04 | V0 | 0 of 3 |
| Installation033-D9 | 10% | — | Draft | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDean, SCA AcademyP-014ab.alharbi@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2027-12-10 | V0 | 0 of 3 |
| Testing & commissioning033-D10 | 10% | — | Draft | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2028-02-16 | V0 | 0 of 3 |
| Provisional acceptance033-D11 | 7% | — | Draft | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDean, SCA AcademyP-014ab.alharbi@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2028-04-23 | V0 | 0 of 3 |
| Final acceptance033-D12 | 7% | — | Draft | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.sa | Eng. Abdulrahman S. Al-Harbi | 2028-06-30 | V0 | 0 of 3 |
| Total · 12 | 100% |