Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-033On hold3PlanningConstruction

Wadi Al-Dawasir Vocational Qualification Centre

Add to watchlist

A permanent training and skills-test centre for the south of the Riyadh region, waiting for the land handover and title deed.

Budget (BAC)

SAR 210M

Actual cost

SAR 4.2M

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 210M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

184 days behind baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution15 July 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate31 December 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 March 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate15 July 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project management plan

One plan bringing the schedule, deliverables, risks, communications, quality and benefits together from the project’s records, approved through the plan’s chain.

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Project management plan

Schedule, deliverables, risks, communications, quality and benefits

Form no.
SCA-PMO-F05
Template edition
2.0
Version
V1
Form date
⁦2026-03-26⁩
Hijri
7 Shawwal 1447 AH
In approvalPRJ-2026-033Wadi Al-Dawasir Vocational Qualification Centre

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-033
Project
Wadi Al-Dawasir Vocational Qualification Centre
Portfolio
Academy & Qualification Centres Portfolio
Sector
Qualification & Training Sector
Sponsor
Eng. Turki A. Al-Anazi
Project manager
Eng. Shahad M. Al-Malki

1ScheduleAuto-filled

From the project schedule and its approved baseline.

Start

⁦2026-03-01⁩

Baseline finish

⁦2028-06-30⁩

Forecast finish

⁦2028-12-31⁩

SPI

1.00

MilestonePlannedForecastSlip
Project plan approved⁦2026-08-24⁩⁦2027-02-15⁩+175 days
Designs approved⁦2027-01-06⁩⁦2027-07-03⁩+178 days
Build complete⁦2027-07-28⁩⁦2028-01-26⁩+182 days
Testing & acceptance complete⁦2028-02-16⁩⁦2028-08-20⁩+186 days
Final handover⁦2028-06-30⁩⁦2029-01-05⁩+189 days

2DeliverablesAuto-filled

DeliverableWeightDueOwner
Project plan & baseline⁦2%⁩⁦2026-06-17⁩Eng. Shahad M. Al-Malki
Monitoring & reporting⁦3%⁩⁦2026-08-24⁩Eng. Abdulrahman S. Al-Harbi
Detailed design⁦6%⁩⁦2026-10-30⁩Eng. Abdulrahman S. Al-Harbi
Permits & approvals⁦6%⁩⁦2027-01-06⁩Eng. Turki A. Al-Anazi
Site works & excavation⁦13%⁩⁦2027-03-15⁩Eng. Turki A. Al-Anazi
Structure⁦13%⁩⁦2027-05-21⁩Eng. Shahad M. Al-Malki
Finishes⁦13%⁩⁦2027-07-28⁩Eng. Abdulrahman S. Al-Harbi
Supply⁦10%⁩⁦2027-10-04⁩Eng. Shahad M. Al-Malki
Installation⁦10%⁩⁦2027-12-10⁩Eng. Abdulrahman S. Al-Harbi
Testing & commissioning⁦10%⁩⁦2028-02-16⁩Eng. Turki A. Al-Anazi
Provisional acceptance⁦7%⁩⁦2028-04-23⁩Eng. Abdulrahman S. Al-Harbi
Final acceptance⁦7%⁩⁦2028-06-30⁩Eng. Turki A. Al-Anazi
Accepted with a certificate⁦2%⁩——

3RisksAuto-filled

CodeRiskScoreResponseOwner
RSK-0044Late land handover and title deed from the owning entity in Wadi Al-Dawasir20EscalateEng. Shahad M. Al-Malki

4CommunicationsAuto-filled

AudienceNeedFrequencyOwner
Project sponsorStatus and decisions neededMonthlyEng. Shahad M. Al-Malki
Project ownerDeliverable status and acceptance datesFortnightlyEng. Shahad M. Al-Malki
PMOData and indicator updatesWeeklyEng. Shahad M. Al-Malki
BeneficiariesWhat changes and whenAt each milestoneEng. Shahad M. Al-Malki
Team memberRoleAllocation
Eng. Shahad M. Al-MalkiProject manager (on hold)⁦10%⁩

5QualityAuto-filled

  • Peer review of every deliverable before acceptance
  • Written acceptance criteria for every deliverable
  • A PMO audit at every gate

6BenefitsAuto-filled

BenefitBaselineTargetOwner
No benefits recorded

Approval logChain: Project management plan approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Shahad M. Al-MalkiDirector, Academy FacilitiesSubmitted—⁦2026-10-23⁩ 10:01
2Methodology review — PMOMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2026-10-25⁩ 12:03
3Technical acceptance — project ownerTechnical acceptanceApproval engineProject ownerPre-breach alert—⁦2026-10-28⁩ 08:00

Signatures

Methodology review — PMO

Ghada A. Al-Shahrani

Approved⁦2026-10-25⁩

Technical acceptance — project owner

Eng. Abdulrahman S. Al-Harbi

Awaiting decision

Cash flow & financial commitment

Munirah A. Al-Khalidi

Later

Sponsor approval

Eng. Turki A. Al-Anazi

Later

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F05 · version V1

Project management plan

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project management plan approval · version ⁦1⁩

Submitted by Eng. Shahad M. Al-Malki on ⁦2026-10-23⁩

  1. Methodology review

    Methodology review — PMO

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2026-10-25⁩ at ⁦12:03⁩

  2. Technical acceptance

    Technical acceptance — project owner

    Eng. Abdulrahman S. Al-Harbi · Project owner

    Delegated to Eng. Shahad M. Al-Malki

    Due todayAction time limit about to lapse · Limit 3 working daysLimit 3 working days · Due ⁦2026-10-28⁩

    Pre-breach alert at ⁦70%⁩ — sent ⁦2026-10-28⁩

    Waiting on Eng. Shahad M. Al-Malki
  3. Financial approval

    Cash flow & financial commitment

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Delegated to Khalid N. Al-Mutairi

    Limit 2 working days · Expected by ⁦2026-11-01⁩

  4. Technical acceptance

    Sponsor approval

    Eng. Turki A. Al-Anazi · Project sponsor

    Limit 3 working days · Expected by ⁦2026-11-04⁩

Steps that do not apply to this record

  • Plan aligned with the contracts — the condition «Contract link?» does not hold

Previous versions

Every version is kept with its status and what changed.

  1. V2In approval⁦2026-03-26⁩

    Approved with the baseline

    • Schedule and cost baseline approved

    Eng. Shahad M. Al-Malki

  2. V1Returned for editCurrent⁦2026-03-12⁩

    First draft — returned to complete the quality plan

    • Plan from the methodology template

    Eng. Shahad M. Al-Malki