AI insight
95% chance of a further slip within 30 days
From the SPI trend (0.74), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.
Rebuilding the Eastern & Northern branch office and adding a new wing with 28 training and skills-test halls.
Budget (BAC)
Actual cost
81% of budget
Progress
Estimate at completion
SAR +78.5M
SPI · CPI
Forecast finish
126 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure13 July 2026
A weighted index, not just percent complete; each dimension leads to the tab that explains it.
Health index
45
Critical
Index over the last six reports
May to October 2026
No material change in the health dimensions over the period.
AI insight
From the SPI trend (0.74), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.
Generated from the live project data
The project is behind plan: 68% done against 92% planned.
SPI 0.74, CPI 0.84.
How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.
The main objective and initiative, the secondary links, and the project’s contribution to its initiative.
Main initiative
SI-3.2.1Rehabilitate existing branches & centres
The project’s share of the initiative’s project budget (2 projects)
Secondary links
Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.
Counted
68%Awaiting acceptance 9%
Not handed in 23%
8 deliverables accepted
1 deliverable under inspection or acceptance
Corrective planCP-2026-02
Approved — under wayOverdue: 1
The main contractor’s cash-flow distress and unpaid subcontractors, the underground tanks failing the tightness test, and training & test hall wing changes never shown to Civil Defence
Actions
1 of 5 done
Next: Appoint an independent financial adviser to audit contractor liquidity · Khalid N. Al-Mutairi · 2026-10-20
Days won back
0 of 45
With the plan: 2027-02-03
4 of 5 milestones complete
Earned-value curve
Planned, earned and actual to the data date, cumulative, with the forecast cost tail
Commitments are 98% of budget
1 approval and 3 open actions on this project
From «My actions» for this project
3 open
Cost and schedule impact
3 open risks, exposure SAR 53.6M
Impact
1 escalated
8 of 12 approved
4 members