PRJ-2026-004Critical4ExecutionConstruction

Al-Khobar Branch — Rehabilitation & Extension

Remove from watchlist

Rebuilding the Eastern & Northern branch office and adding a new wing with 28 training and skills-test halls.

Early warning: ⁦95%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 412M

Actual cost

SAR 333.5M

⁦81%⁩ of budget

Progress

⁦68%⁩Awaiting acceptance ⁦9%⁩

Estimate at completion

SAR 490.5M

SAR +78.5M

SPI · CPI

0.74Schedule performance index · 0.740.84Cost performance index · 0.84

Forecast finish

⁦2027-02-03⁩

126 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure13 July 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 November 2023Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate14 January 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate20 June 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate13 July 2026Closure · Not startedClosure · Not started

Project management plan

One plan bringing the schedule, deliverables, risks, communications, quality and benefits together from the project’s records, approved through the plan’s chain.

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Project management plan

Schedule, deliverables, risks, communications, quality and benefits

Form no.
SCA-PMO-F05
Template edition
2.0
Version
V2
Form date
⁦2024-02-08⁩
Hijri
27 Rajab 1445 AH
ApprovedPRJ-2026-004Al-Khobar Branch — Rehabilitation & Extension

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-004
Project
Al-Khobar Branch — Rehabilitation & Extension
Portfolio
Building Rehabilitation & Sustainability Portfolio
Sector
Corporate Support Sector
Sponsor
Eng. Turki A. Al-Anazi
Project manager
Eng. Waleed O. Al-Juhani

1ScheduleAuto-filled

From the project schedule and its approved baseline.

Start

⁦2024-01-14⁩

Baseline finish

⁦2026-09-30⁩

Forecast finish

⁦2027-02-03⁩

SPI

0.74

MilestonePlannedForecastSlip
Project plan approved⁦2024-08-05⁩⁦2024-11-17⁩+104 days
Designs approved⁦2025-01-09⁩⁦2025-07-11⁩+183 days
Build complete⁦2025-09-02⁩⁦2026-07-01⁩+302 days
Testing & acceptance complete⁦2026-04-26⁩⁦2027-02-16⁩+296 days
Final handover⁦2026-09-30⁩⁦2027-03-08⁩+159 days

2DeliverablesAuto-filled

DeliverableWeightDueOwner
Project plan & baseline⁦3%⁩⁦2024-05-19⁩Eng. Waleed O. Al-Juhani
Monitoring & reporting⁦3%⁩⁦2024-08-05⁩Eng. Bandar M. Al-Shammari
Detailed design⁦6%⁩⁦2024-10-23⁩Eng. Bandar M. Al-Shammari
Permits & approvals⁦6%⁩⁦2025-01-09⁩Eng. Turki A. Al-Anazi
Site works & excavation⁦13%⁩⁦2025-03-29⁩Eng. Turki A. Al-Anazi
Structure⁦13%⁩⁦2025-06-16⁩Eng. Waleed O. Al-Juhani
Finishes⁦13%⁩⁦2025-09-02⁩Eng. Bandar M. Al-Shammari
Supply⁦11%⁩⁦2025-11-20⁩Eng. Waleed O. Al-Juhani
Installation⁦9%⁩⁦2026-02-06⁩Eng. Bandar M. Al-Shammari
Testing & commissioning⁦9%⁩⁦2026-04-26⁩Eng. Turki A. Al-Anazi
Provisional acceptance⁦7%⁩⁦2026-07-13⁩Eng. Bandar M. Al-Shammari
Final acceptance⁦7%⁩⁦2026-09-30⁩Eng. Turki A. Al-Anazi
Accepted with a certificate⁦68%⁩——

3RisksAuto-filled

CodeRiskScoreResponseOwner
RSK-0021Main contractor cash-flow distress and unpaid subcontractors25EscalateEng. Waleed O. Al-Juhani
RSK-0022Fire-fighting and evacuation systems failing Civil Defence requirements15MitigateEng. Mishari K. Al-Otaibi
RSK-0023Central HVAC failures during commissioning12MitigateEng. Waleed O. Al-Juhani

4CommunicationsAuto-filled

AudienceNeedFrequencyOwner
Project sponsorStatus and decisions neededMonthlyEng. Waleed O. Al-Juhani
Project ownerDeliverable status and acceptance datesFortnightlyEng. Waleed O. Al-Juhani
PMOData and indicator updatesWeeklyEng. Waleed O. Al-Juhani
BeneficiariesWhat changes and whenAt each milestoneEng. Waleed O. Al-Juhani
Team memberRoleAllocation
Eng. Waleed O. Al-JuhaniProject manager⁦70%⁩
Eng. Turki A. Al-AnaziProject sponsor⁦20%⁩
Haifa S. Al-RuwailiFinancial analyst⁦15%⁩
—Contractor site manager⁦110%⁩

5QualityAuto-filled

Quality leadAuto-filled
Eng. Adel S. Al-Amoudi
Review cadenceAuto-filled
Weekly site inspection; cube tests for every pour in the new wing
Next reviewAuto-filled
⁦2026-11-08⁩
Quality criterionThresholdNowMet
Structural concrete strengthC40 at 28 daysC35 at the chiller basesNo
Underground water-tank tightness testLevel drop under 0.1% in 24 h0.6% in tank 2No
Chiller and equipment conformityA conformity certificate per delivery12 of 12Yes

6BenefitsAuto-filled

BenefitBaselineTargetOwner
Training hours accommodated per year0 hours / year43800 hours / yearEng. Mishari K. Al-Otaibi

Approval logChain: Project management plan approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceSubmitted—⁦2024-02-08⁩ 14:17
2Methodology review — PMOMethodology reviewGhada A. Al-ShahraniPMO — analystApprovedComplete against the project management plan template.⁦2024-02-12⁩ 10:19
3Technical acceptance — project ownerTechnical acceptanceEng. Bandar M. Al-ShammariProject ownerApproved—⁦2024-02-15⁩ 11:26
4Cash flow & financial commitmentFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2024-02-18⁩ 09:12
5Plan aligned with the contractsFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2024-02-20⁩ 10:49
6Sponsor approvalTechnical acceptanceEng. Turki A. Al-AnaziProject sponsorApproved—⁦2024-02-25⁩ 14:47

Signatures

Methodology review — PMO

Ghada A. Al-Shahrani

Approved⁦2024-02-12⁩

Technical acceptance — project owner

Eng. Bandar M. Al-Shammari

Approved⁦2024-02-15⁩

Cash flow & financial commitment

Munirah A. Al-Khalidi

Approved⁦2024-02-18⁩

Plan aligned with the contracts

Mazen A. Al-Hazmi

Approved⁦2024-02-20⁩

Sponsor approval

Eng. Turki A. Al-Anazi

Approved⁦2024-02-25⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F05 · version V2

Project management plan

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project management plan approval · version ⁦1⁩

Submitted by Eng. Waleed O. Al-Juhani on ⁦2024-02-08⁩

  1. Methodology review

    Methodology review — PMO

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2024-02-12⁩ at ⁦10:19⁩

    Complete against the project management plan template.

  2. Technical acceptance

    Technical acceptance — project owner

    Eng. Bandar M. Al-Shammari · Project owner

    Approved · ⁦2024-02-15⁩ at ⁦11:26⁩

  3. Financial approval

    Cash flow & financial commitment

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2024-02-18⁩ at ⁦09:12⁩

  4. Financial approval

    Plan aligned with the contracts

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2024-02-20⁩ at ⁦10:49⁩

  5. Technical acceptance

    Sponsor approval

    Eng. Turki A. Al-Anazi · Project sponsor

    Approved · ⁦2024-02-25⁩ at ⁦14:47⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2024-02-08⁩

    Approved with the baseline

    • Schedule and cost baseline approved

    Eng. Waleed O. Al-Juhani

  2. V1Returned for edit⁦2024-01-25⁩