Portfolio · PF-SUS

Building Rehabilitation & Sustainability Portfolio

Off track

Rehabilitating and extending the Al-Khobar branch and existing training centres, solar power and energy efficiency.

What-if scenarios
Approved budget
SAR 672M

incl. SAR 22M unallocated reserve

Actual spend
SAR 470.5M

⁦70%⁩ of budget

EAC
SAR 726M+8.0%

Estimate at completion

Expected value
SAR 1.1B

⁦10%⁩ realised

Health score
61−5

was ⁦66⁩ in May

Manager

Eng. Mishari K. Al-Otaibi

Director, Sustainability & Energy Efficiency

Owner

Eng. Bandar M. Al-Shammari

Director General, Facilities & Premises

Programmes5 projects

Building Rehabilitation & Efficiency Programme⁦55%⁩
On track 3Critical 1On hold 1

AI insight

Every active project in the portfolio is on track

No project is off track or critical; the weakest health dimension is “Risk” at ⁦40⁩.

Confidence⁦78%⁩

Weighted portfolio progress

Σ each project’s relative weight × its actual progress, under the approved project weight model

What each project adds to portfolio progress

The project’s weight from the model, its relative weight among the portfolio’s counted projects, and what it adds

ProjectProject weightRelative weightActual progressWeight × progress
Al-Khobar Branch — Rehabilitation & Extension83.0⁦24.4%⁩⁦68%⁩⁦16.6%⁩
Solar Power for SCA Buildings & Centres71.0⁦20.9%⁩⁦58%⁩⁦12.1%⁩
Khamis Mushait Training Centre Rehabilitation65.0⁦19.1%⁩⁦97%⁩⁦18.5%⁩
Al-Jouf Training Centre Rehabilitation62.0⁦18.2%⁩⁦36%⁩⁦6.6%⁩
Energy Retrofit of Existing SCA Buildings (ESCO)Suspended — progress frozen59.0⁦17.4%⁩⁦6%⁩⁦1.0%⁩
Portfolio progress⁦54.9%⁩

How it is computed

⁦54.9%⁩

Portfolio progress = Σ (project relative weight × actual progress). Relative weight = the project’s weight ÷ the weights of the counted projects, so they add up to 100%.

  • · Proposed and cancelled projects never count.
  • · Left out of this portfolio now: ⁦0⁩
  • · For comparison: weighting by budget alone gives ⁦64.4%⁩

Suspended projects

Open the project weight model

Portfolio health & performance

The health score from eight weighted dimensions, and the schedule and cost indices over six months.

Health-score breakdown

Score × weight = points

61At risk
DimensionScoreWeightPoints
Schedule52⁦20%⁩10.4
Cost64⁦20%⁩12.8
Risk40⁦15%⁩6.0
Scope72⁦10%⁩7.2
Quality74⁦10%⁩7.4
Resources60⁦10%⁩6.0
Stakeholders76⁦5%⁩3.8
Benefits74⁦10%⁩7.4
Total61

Health-score trend

May – October 2026

6661

Financial & schedule performance

May – October 2026

Both indices over time

  • Schedule performance index
  • Cost performance index

Portfolio project map

risk across, strategic value up, bubble size by budget. Click a bubble for a quick look at the project.

Portfolio project map

  • On track
  • Critical
  • On hold
Approved budget · SAR 412M

Funding priority order

Rank the projects for funding; your order is kept and goes to the 2027 planning cycle.

  1. 1Al-Khobar Branch — Rehabilitation & ExtensionPRJ-2026-004·Priority score 87Critical
  2. 2Solar Power for SCA Buildings & CentresPRJ-2026-010·Priority score 83On track
  3. 3Al-Jouf Training Centre RehabilitationPRJ-2026-025·Priority score 70On track
  4. 4Khamis Mushait Training Centre RehabilitationPRJ-2026-036·Priority score 69On track
  5. 5Energy Retrofit of Existing SCA Buildings (ESCO)PRJ-2026-026·Priority score 58On hold

Portfolio priorities 2026–2027

  • Rescue the Al-Khobar branch rehabilitationCritical — an executive-committee task force is in place.
  • Lift rehabilitated existing branches and centres to 55%43% today — behind the path to the 2027 target.
  • Secure funding for the ESCO energy retrofitOn hold since the executive committee’s 6 October decision.

Objectives & KPIs

Why the portfolio exists: the strategic objectives it serves and the KPIs its projects move.

Budget & value

Where the budget goes, why the forecast differs from it, and the value it returns.

From approved budget to estimate at completion

Each programme’s gap between its projects’ budget and their forecast

From approved budget to estimate at completion
  • Total
  • Increase
  • Decrease
From approved budget to estimate at completion
CategoryChangeRunning total
Approved budgetSAR 672MSAR 672M
Unallocated reserve−SAR 22MSAR 650M
Building Rehabilitation & Efficiency Programme+SAR 76MSAR 726M
Estimate at completionSAR 726MSAR 726M

Budget use

470.5M/ 672M54Mprojected overrun(⁦8.0%⁩)
Actual spend
470.5M
Committed
595.8M
Approved budget
672M
Estimate at completion
726M

Expected-value mix

Expected-value mix

SAR 1.1B

Expected value

  • Sustainability (ESG)SAR 484M⁦44%⁩
  • Cost savingSAR 418M⁦38%⁩
  • Beneficiary satisfactionSAR 198M⁦18%⁩
Expected-value mix
CategoryValueShare
Sustainability (ESG)SAR 484M⁦44%⁩
Cost savingSAR 418M⁦38%⁩
Beneficiary satisfactionSAR 198M⁦18%⁩
TotalSAR 1.1B⁦100%⁩

SAR 104.3M

Expected value SAR 1.1B

⁦73%⁩ of what was planned by today

Programmes & projects

A programme’s performance is computed from its projects. Click a project for a quick look.

⁦5⁩ results
Export CSV
Al-Khobar Branch — Rehabilitation & ExtensionPRJ-2026-004PG-094ExecutionCritical⁦68%⁩⁦24.4%⁩P1P1 · Top priority — score ⁦87⁩ of 100412M490.5M⁦+19.0%⁩0.74Schedule performance index · 0.740.84Cost performance index · 0.84Risk score · Weak
Solar Power for SCA Buildings & CentresPRJ-2026-010PG-094ExecutionOn track⁦58%⁩⁦20.9%⁩P1P1 · Top priority — score ⁦83⁩ of 10096M95.1M⁦−1.0%⁩1.02Schedule performance index · 1.021.01Cost performance index · 1.01Risk score · Good
Khamis Mushait Training Centre RehabilitationPRJ-2026-036PG-095ClosureOn track⁦97%⁩⁦19.1%⁩P2P2 · High priority — score ⁦69⁩ of 10067M66.3M⁦−1.0%⁩0.98Schedule performance index · 0.981.01Cost performance index · 1.01Risk score · Excellent
Al-Jouf Training Centre RehabilitationPRJ-2026-025PG-094ExecutionOn track⁦36%⁩⁦18.2%⁩P2P2 · High priority — score ⁦70⁩ of 10042M41.2M⁦−2.0%⁩1.03Schedule performance index · 1.031.02Cost performance index · 1.02Risk score · Good
Energy Retrofit of Existing SCA Buildings (ESCO)PRJ-2026-026PG-093PlanningOn hold⁦8%⁩⁦17.4%⁩P3P3 · Medium priority — score ⁦58⁩ of 10033M33M⁦0.0%⁩0.89Schedule performance index · 0.891.00Cost performance index · 1.00Risk score · Weak
Total · 5650M726M
⁦1⁩–⁦5⁩ of ⁦5⁩

Portfolio risks

Open threats across the portfolio’s projects. Click a cell on the map to filter the list.

Latest on this portfolio

6 October 2026

  1. Rejection: Executive Committee Hold DEC-2026-035ESCO energy retrofit put on hold pending funding

    2026-10-06 10:00

30 September 2026

  1. Gate decision: Project Approval Committee Go DEC-2026-034Solar for SCA buildings passes the mid-execution review

    2026-09-30 10:00

22 September 2026

  1. Approval: Executive Committee Approved DEC-2026-032Task force formed for the Al-Khobar branch contractor distress