AI insight
No early warning on this project
Only a 12% chance of a further slip on current trends.
Rehabilitating the Khamis Mushait training centre — fire and alarm systems and training halls.
Budget (BAC)
Actual cost
96% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
12 days behind baseline
ClosureStage 5 of 5
A weighted index, not just percent complete; each dimension leads to the tab that explains it.
Health index
88
Solid
Index over the last six reports
May to October 2026
No material change in the health dimensions over the period.
AI insight
Only a 12% chance of a further slip on current trends.
Generated from the live project data
The project is close to plan: 97% done against 99% planned.
SPI 0.98, CPI 1.01.
How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.
The main objective and initiative, the secondary links, and the project’s contribution to its initiative.
Main initiative
SI-3.2.1Rehabilitate existing branches & centres
The project’s share of the initiative’s project budget (2 projects)
Secondary links
No secondary links
Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.
Counted
97%Awaiting acceptance 3%
Not handed in 0%
11 deliverables accepted
1 deliverable under inspection or acceptance
4 of 5 milestones complete
Earned-value curve
Planned, earned and actual to the data date, cumulative, with the forecast cost tail
Commitments are 99% of budget
1 approval and 0 open actions on this project
From «My actions» for this project
0 open
Cost and schedule impact
1 open risk, exposure SAR 600K
Impact
0 escalated
11 of 12 approved
1 member