PRJ-2026-036On track5ClosureConstruction

Khamis Mushait Training Centre Rehabilitation

Add to watchlist

Rehabilitating the Khamis Mushait training centre — fire and alarm systems and training halls.

Budget (BAC)

SAR 67M

Actual cost

SAR 64.3M

⁦96%⁩ of budget

Progress

⁦97%⁩Awaiting acceptance ⁦3%⁩

Estimate at completion

SAR 66.3M

SPI · CPI

0.98Schedule performance index · 0.981.01Cost performance index · 1.01

Forecast finish

⁦2026-11-12⁩

12 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 August 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate6 October 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate4 February 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate1 September 2026Closure · Current stageClosure · Current stage

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

+6

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is close to plan: ⁦97%⁩ done against ⁦99%⁩ planned.

SPI ⁦0.98⁩, CPI ⁦1.01⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: Specialised, Value-adding ServicesSO-3.2Efficient, sustainable SCA facilities

Main initiative

SI-3.2.1Rehabilitate existing branches & centres

Contribution to the initiative⁦14%⁩

The project’s share of the initiative’s project budget (2 projects)

Secondary links

No secondary links

Annual work-plan line
WP-2024-036
Classification
Operational

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦97%⁩

Awaiting acceptance ⁦3%⁩

Not handed in ⁦0%⁩

11 deliverables accepted

  • Site works & excavation⁦13%⁩
  • Structure⁦13%⁩
  • Finishes⁦13%⁩
  • Supply⁦11%⁩
  • Installation⁦11%⁩
  • Testing & commissioning⁦11%⁩
  • Provisional acceptance⁦7%⁩
  • Detailed design⁦6%⁩

1 deliverable under inspection or acceptance

  • Final acceptance⁦3%⁩

Progress & earned value

⁦4⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦99%⁩ of budget

64.3M/ 67M663Kprojected saving(⁦1.0%⁩)
Actual spend
64.3M
Committed
66.2M
Approved budget
67M
Estimate at completion
66.3M

Next milestones

  • Closure⁦2026-11-12⁩was ⁦2026-10-31⁩At risk

Waiting on someone

⁦1⁩ approval and ⁦0⁩ open actions on this project

Approvals & requests

From «My actions» for this project

Actions

⁦0⁩ open

  • No actions on this project

Change requests

Cost and schedule impact

  • No change requests

Risks & impediments

1 open risk, exposure SAR 600K

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩1Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩RSK-0045Preliminary-handover snags on the fire and alarm systemsProbability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High0
  • Medium0
  • Low1

Open impediments

⁦0⁩ escalated

  • No open impediments

Deliverables

⁦11⁩ of ⁦12⁩ approved

  • Project plan & baseline036-D1 · V1 · CRT-036-01⁦3%⁩Eng. Waleed O. Al-Juhani⁦2025-01-10⁩2025-01-1010 Rajab 1446 AHApproved
  • Monitoring & reporting036-D2 · V1 · CRT-036-02⁦3%⁩Eng. Bandar M. Al-Shammari⁦2025-03-11⁩2025-03-1111 Ramadan 1446 AHApproved
  • Detailed design036-D3 · V1 · CRT-036-03⁦6%⁩Eng. Bandar M. Al-Shammari⁦2025-05-10⁩2025-05-1012 Dhuʻl-Qiʻdah 1446 AHApproved
  • Permits & approvals036-D4 · V1 · CRT-036-04⁦6%⁩Eng. Turki A. Al-Anazi⁦2025-07-09⁩2025-07-0914 Muharram 1447 AHApproved
  • Site works & excavation036-D5 · V1 · CRT-036-05⁦13%⁩Eng. Turki A. Al-Anazi⁦2025-09-07⁩2025-09-0715 Rabiʻ I 1447 AHApproved
  • Structure036-D6 · V1 · CRT-036-06⁦13%⁩Eng. Waleed O. Al-Juhani⁦2025-11-05⁩2025-11-0514 Jumada I 1447 AHApproved
  • Finishes036-D7 · V1 · CRT-036-07⁦13%⁩Eng. Bandar M. Al-Shammari⁦2026-01-04⁩2026-01-0415 Rajab 1447 AHApproved
  • Supply036-D8 · V1 · CRT-036-08⁦11%⁩Eng. Waleed O. Al-Juhani⁦2026-03-05⁩2026-03-0516 Ramadan 1447 AHApproved
  • Installation036-D9 · V1 · CRT-036-09⁦11%⁩Eng. Bandar M. Al-Shammari⁦2026-05-04⁩2026-05-0417 Dhuʻl-Qiʻdah 1447 AHApproved
  • Testing & commissioning036-D10 · V1 · CRT-036-10⁦11%⁩Eng. Turki A. Al-Anazi⁦2026-07-03⁩2026-07-0318 Muharram 1448 AHApproved
  • Provisional acceptance036-D11 · V1 · CRT-036-11⁦7%⁩Eng. Bandar M. Al-Shammari⁦2026-09-01⁩2026-09-0119 Rabiʻ I 1448 AHApproved
  • Final acceptance036-D12 · V1⁦3%⁩Eng. Turki A. Al-AnaziIn 3 days2026-10-3120 Jumada I 1448 AHSubmitted

Team, contracts & documents

Team

1 member

Eng. Waleed O. Al-Juhani · Director, Facilities Operations & Maintenance
  • Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceProject managerP-021w.aljuhani@sca.sa⁦30%⁩