The objective’s weakest KPI, “SCA centres operating in owned buildings”, is at 78% of its target, and its heaviest project, “Al-Khobar Branch — Rehabilitation & Extension”, is Critical. Fixing that one path lifts the objective more than any other action.
What we are doing to bring the KPI back on track, who owns it, and by when.
Move the Khamis Mushait training centre from the leased building into the rehabilitated one at acceptance
Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021·w.aljuhani@sca.saDue 2026-10-253 days overdue2026-10-25·14 Jumada I 1448 AHK-3.2.3Khamis Mushait Training Centre Rehabilitation
Overdue
Settle the Al-Khobar branch contractor claim through the dispute board so the training-hall wing resumes
Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021·w.aljuhani@sca.saDue 2026-11-15In 18 days2026-11-15·5 Jumada II 1448 AHK-3.2.3Al-Khobar Branch — Rehabilitation & Extension
In progress
Fast-track grid connection of the solar plants on 12 SCA buildings and centres
Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028·m.alotaibi@sca.saDue 2026-12-15In 48 days2026-12-15·6 Rajab 1448 AHK-3.2.1Solar Power for SCA Buildings & Centres
Open
Challenges & notes
What holds the objective back and what leadership should know.
Challenge
Cash distress at the Al-Khobar branch contractor has stopped the training-hall wing — the main reason rehabilitation is behind.
Eng. Waleed O. Al-Juhani · 2026-10-18
Note
The energy retrofit of existing SCA buildings is on hold pending the Finance-approved ESCO contract model.