The project with the most weight on this KPI is “Al-Khobar Branch — Rehabilitation & Extension”, with 86% of the linked budget, and it is Critical. Speeding it up is the fastest way to close the gap before December.
What we are doing to bring the KPI back on track, who owns it, and by when.
Move the Khamis Mushait training centre from the leased building into the rehabilitated one at acceptance
Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021·w.aljuhani@sca.saDue 2026-10-253 days overdue2026-10-25·14 Jumada I 1448 AHKhamis Mushait Training Centre Rehabilitation
Overdue
Settle the Al-Khobar branch contractor claim through the dispute board so the training-hall wing resumes
Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021·w.aljuhani@sca.saDue 2026-11-15In 18 days2026-11-15·5 Jumada II 1448 AHAl-Khobar Branch — Rehabilitation & Extension
In progress
Comments
The owner, the Performance Measurement Office and leadership discussing the readings.
Eng. Bandar M. Al-ShammariDirector General, Facilities & Premises2026-10-19 12:30
The KPI will not move until the Al-Khobar training-hall wing is handed over and the centre moves in. We need a decision on the claim this month.
Eng. Waleed O. Al-JuhaniDirector, Facilities Operations & Maintenance2026-10-20 08:15
October’s reading comes from the facilities system; I will confirm it once the open leases are reconciled.