PRJ-2026-010On track4ExecutionConstruction

Solar Power for SCA Buildings & Centres

Add to watchlist

6 MW of rooftop and carport solar across 14 SCA buildings and centres, the largest a ground array at the Tabuk site.

Budget (BAC)

SAR 96M

Actual cost

SAR 55.1M

⁦57%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 95.1M

SPI · CPI

1.02Schedule performance index · 1.021.01Cost performance index · 1.01

Forecast finish

⁦2027-04-22⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure26 February 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate1 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate2 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate6 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate26 February 2027Closure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

+5

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is close to plan: ⁦58%⁩ done against ⁦57%⁩ planned.

SPI ⁦1.02⁩, CPI ⁦1.01⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: Specialised, Value-adding ServicesSO-3.2Efficient, sustainable SCA facilities

Main initiative

SI-3.2.2Clean energy & efficient buildings

Contribution to the initiative⁦74%⁩

The project’s share of the initiative’s project budget (2 projects)

Secondary links

No secondary links

Annual work-plan line
WP-2025-010
Classification
Operational

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦58%⁩

Awaiting acceptance ⁦10%⁩

Not handed in ⁦32%⁩

7 deliverables accepted

  • Site works & excavation⁦13%⁩
  • Structure⁦13%⁩
  • Finishes⁦13%⁩
  • Detailed design⁦7%⁩
  • Permits & approvals⁦6%⁩
  • Project plan & baseline⁦3%⁩
  • Monitoring & reporting⁦3%⁩

1 deliverable under inspection or acceptance

  • Supply⁦10%⁩

Progress & earned value

⁦3⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦90%⁩ of budget

55.1M/ 96M950Kprojected saving(⁦1.0%⁩)
Actual spend
55.1M
Committed
86.5M
Approved budget
96M
Estimate at completion
95.1M

Next milestones

  • Provisional acceptance⁦2027-02-20⁩was ⁦2027-02-26⁩On track
  • Closure⁦2027-04-22⁩was ⁦2027-04-30⁩On track

Waiting on someone

⁦0⁩ approvals and ⁦0⁩ open actions on this project

Approvals & requests

From «My actions» for this project

  • No approvals pending

Actions

⁦0⁩ open

  • No actions on this project

Change requests

Cost and schedule impact

  • No change requests

Risks & impediments

1 open risk, exposure SAR 5.2M

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High0
  • Medium0
  • Low0

Open impediments

⁦0⁩ escalated

  • No open impediments

Deliverables

⁦7⁩ of ⁦12⁩ approved

  • Project plan & baseline010-D1 · V1 · CRT-010-01⁦3%⁩Eng. Mishari K. Al-Otaibi⁦2025-06-10⁩2025-06-1014 Dhuʻl-Hijjah 1446 AHApproved
  • Monitoring & reporting010-D2 · V1 · CRT-010-02⁦3%⁩Eng. Bandar M. Al-Shammari⁦2025-08-12⁩2025-08-1218 Safar 1447 AHApproved
  • Detailed design010-D3 · V1 · CRT-010-03⁦7%⁩Eng. Bandar M. Al-Shammari⁦2025-10-13⁩2025-10-1321 Rabiʻ II 1447 AHApproved
  • Permits & approvals010-D4 · V1 · CRT-010-04⁦6%⁩Eng. Turki A. Al-Anazi⁦2025-12-15⁩2025-12-1524 Jumada II 1447 AHApproved
  • Site works & excavation010-D5 · V1 · CRT-010-05⁦13%⁩Eng. Turki A. Al-Anazi⁦2026-02-16⁩2026-02-1628 Shaʻban 1447 AHApproved
  • Structure010-D6 · V1 · CRT-010-06⁦13%⁩Eng. Mishari K. Al-Otaibi⁦2026-04-19⁩2026-04-192 Dhuʻl-Qiʻdah 1447 AHApproved
  • Finishes010-D7 · V1 · CRT-010-07⁦13%⁩Eng. Bandar M. Al-Shammari⁦2026-06-21⁩2026-06-216 Muharram 1448 AHApproved
  • Supply010-D8 · V1⁦10%⁩Eng. Mishari K. Al-Otaibi66 days overdue2026-08-2310 Rabiʻ I 1448 AHSubmitted
  • Installation010-D9 · V0⁦9%⁩Eng. Bandar M. Al-Shammari4 days overdue2026-10-2413 Jumada I 1448 AHDraft
  • Testing & commissioning010-D10 · V0⁦9%⁩Eng. Turki A. Al-AnaziIn 59 days2026-12-2617 Rajab 1448 AHDraft
  • Provisional acceptance010-D11 · V0⁦7%⁩Eng. Bandar M. Al-ShammariIn 121 days2027-02-2619 Ramadan 1448 AHDraft
  • Final acceptance010-D12 · V0⁦7%⁩Eng. Turki A. Al-AnaziIn 184 days2027-04-3023 Dhuʻl-Qiʻdah 1448 AHDraft

Team, contracts & documents

Team

2 members

Eng. Mishari K. Al-Otaibi · Director, Sustainability & Energy EfficiencyEng. Bandar M. Al-Shammari · Director General, Facilities & Premises
  • Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyProject managerP-028m.alotaibi@sca.sa⁦45%⁩
  • Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesProject sponsorP-013b.alshammari@sca.sa⁦15%⁩

Documents

  • No documents yet

Meetings

  • No meetings scheduled
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close