Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-010On track4ExecutionConstruction

Solar Power for SCA Buildings & Centres

Add to watchlist

6 MW of rooftop and carport solar across 14 SCA buildings and centres, the largest a ground array at the Tabuk site.

Budget (BAC)

SAR 96M

Actual cost

SAR 55.1M

⁦57%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 95.1M

SPI · CPI

1.02Schedule performance index · 1.021.01Cost performance index · 1.01

Forecast finish

⁦2027-04-22⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure26 February 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate1 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate2 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate6 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate26 February 2027Closure · Not startedClosure · Not started

Project documents by stage

What each stage requires under the RFP, what has been filed and what is missing, and the evidence tied to deliverables.

Open in the repository
  • ⁦0⁩ of ⁦7⁩ mandatory documents due
  • 7 mandatory documents missing
  • No documents

Documents in the project folder

Archived automatically when the project closes, and kept read-only under the retention policy.

Stages and required documents

For each of the five stages, what its gates and forms require: present, missing, or not yet due.

  1. 1Pre-start
    • Project proposal & feasibility studyMandatory· Missing

      Approval gate G1

    • Priority & weight assessmentOptional· Missing

      Annual work plan

  2. 2Initiation
    • Approved project charterMandatory· Missing

      Initiation gate G2

    • Kick-off meeting minutesMandatory· Missing

      Initiation gate G2

  3. 3Planning
    • Project management plan, schedule & baselineMandatory· Missing

      Planning gate G3

    • Contract or purchase orderMandatory· Missing

      Finance & procurement — when there is a contract

    • Technical studies & drawingsOptional· Missing

      Project management plan

  4. 4ExecutionCurrent stage
    • Periodic update cards & status reportsMandatory· Missing

      Periodic update card form

    • Deliverable completion certificatesMandatory· Missing

      Deliverable completion certificate form

    • Corrective plan when off trackOptional· Missing

      Corrective plan form

  5. 5Closure
    • Project closure & handover formMandatory· Not yet due

      Closure gate G4

    • Lessons learnedMandatory· Not yet due

      Closure gate G4

    • Acceptance test resultsOptional· Not yet due

      Deliverable acceptance

Evidence tied to deliverables

Each deliverable with its repository document and the files that prove it.

  • 010-D1Project plan & baselinePRJ-2026-010_1.1_v1.pdfApprovedDeliverable
  • 010-D2Monitoring & reportingPRJ-2026-010_1.2_v1.pdfApprovedDeliverable
  • 010-D3Detailed designPRJ-2026-010_2.1_v1.pdfApprovedDeliverable
  • 010-D4Permits & approvalsPRJ-2026-010_2.2_v1.pdfApprovedDeliverable
  • 010-D5Site works & excavationPRJ-2026-010_3.1_v1.pdfApprovedDeliverable
  • 010-D6StructurePRJ-2026-010_3.2_v1.pdfApprovedDeliverable
  • 010-D7FinishesPRJ-2026-010_3.3_v1.pdfApprovedDeliverable
  • 010-D8SupplyPRJ-2026-010_4.1_v1.pdfIn reviewDeliverable
  • 010-D9InstallationNo evidence filed yetDraftDeliverable
  • 010-D10Testing & commissioningNo evidence filed yetDraftDeliverable
  • 010-D11Provisional acceptanceNo evidence filed yetDraftDeliverable
  • 010-D12Final acceptanceNo evidence filed yetDraftDeliverable