PRJ-2026-010On track4ExecutionConstruction

Solar Power for SCA Buildings & Centres

Add to watchlist

6 MW of rooftop and carport solar across 14 SCA buildings and centres, the largest a ground array at the Tabuk site.

Budget (BAC)

SAR 96M

Actual cost

SAR 55.1M

⁦57%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 95.1M

SPI · CPI

1.02Schedule performance index · 1.021.01Cost performance index · 1.01

Forecast finish

⁦2027-04-22⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure26 February 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate1 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate2 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate6 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate26 February 2027Closure · Not startedClosure · Not started
Fields required by the project’s stage (Execution): 15 fields required now.Field settings

Saudi Contractors Authority

Project charter

Solar Power for SCA Buildings & Centres

APPROVEDV2Approved ⁦2025-02-28⁩

1Project identity

Required at this stage
Project name
Solar Power for SCA Buildings & Centres
Project code
PRJ-2026-010
Project sponsor
Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.sa
Project manager
Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@sca.sa
Project owner
Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.sa
Portfolio & programme
Building Rehabilitation & Sustainability PortfolioBuilding Rehabilitation & Efficiency Programme
Type & methodology
Infrastructure · Construction
Current phase
4Execution

2Background & rationale

Required at this stage

⁦6⁩ MW of rooftop and carport solar across ⁦14⁩ SCA buildings and centres, the largest a ground array at the Tabuk site.

3Objectives

Required at this stage
  1. 1Efficient, sustainable SCA facilities
Serves the strategic objectives:SO-3.2Efficient, sustainable SCA facilities

4Scope

Required at this stage

In scope

  • ⁦6⁩ MW of rooftop and carport solar across ⁦14⁩ SCA buildings and centres, the largest a ground array at the Tabuk site.
  • Saudi Building Code compliance
  • An approved plan to keep contractor services and training running during the works

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

Required at this stage
  1. 1Saudi Building Code compliance
  2. 2An approved plan to keep contractor services and training running during the works
  3. 3Civil-defence requirements

6Deliverables

Required at this stage
1Project management plan⁦2025-04-02⁩
2Main deliverable — stage 1⁦2026-04-09⁩
3Main deliverable — final stage⁦2027-01-10⁩
4Final report⁦2027-04-30⁩

7Key milestones

Required at this stage
  1. Charter approved⁦2025-02-28⁩
  2. Contract signed⁦2025-07-06⁩
  3. 50% of works complete⁦2026-04-09⁩
  4. Provisional acceptance⁦2027-02-26⁩
  5. Closure⁦2027-04-30⁩

8Budget

Required at this stage
  • Main contract⁦72.0%⁩69.1M
  • Supervision & consulting⁦14.1%⁩13.5M
  • Internal team⁦9.0%⁩8.6M
  • Contingency reserve (⁦5%⁩)⁦5.0%⁩4.8M
The owning sector’s approved budgetTotal96M

9Timeline

Required at this stage
Start
2025-03-022 Ramadan 1446 AH
Baseline finish
2027-04-3023 Dhuʻl-Qiʻdah 1448 AH
Duration
⁦26⁩ months

10Key risks

Required at this stage
  • MediumFalling global panel prices allow more capacity within budget

11Constraints

Required at this stage
  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

12Assumptions

Required at this stage
  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

13Stakeholders

Required at this stage
  • Project sponsorDecisions and funding
  • Project ownerAccepts deliverables, owns benefits
  • Project Management Office (PMO)Governance and compliance

14Success criteria

Required at this stage
  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3Target benefits within ⁦12⁩ months

15Governance structure

Required at this stage
  • Change Control BoardApproves scope, cost and schedule changesWeekly
  • PMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly
Version V2 · ⁦4⁩ of ⁦4⁩ signaturesInternal — not for circulation outside the Board