PRJ-2026-010On track4ExecutionConstruction
Solar Power for SCA Buildings & Centres
Add to watchlist6 MW of rooftop and carport solar across 14 SCA buildings and centres, the largest a ground array at the Tabuk site.
Project managerEng. Mishari K. Al-OtaibiProject sponsorEng. Turki A. Al-AnaziProgrammeBuilding Rehabilitation & Efficiency Programme
Budget (BAC)
SAR 96M
Actual cost
SAR 55.1M
57% of budget
Progress
58%Awaiting acceptance 10%
Estimate at completion
SAR 95.1M
SPI · CPI
1.02Schedule performance index · 1.021.01Cost performance index · 1.01
Forecast finish
2027-04-22
On baseline
ExecutionStage 4 of 5
Next gate:Closure26 February 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate1 January 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate2 March 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate6 July 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate26 February 2027Closure · Not startedClosure · Not started