Solar Power for SCA Buildings & Centres
Add to watchlist6 MW of rooftop and carport solar across 14 SCA buildings and centres, the largest a ground array at the Tabuk site.
Budget (BAC)
Actual cost
57% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ExecutionStage 4 of 5
Next gate:Closure26 February 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate1 January 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate2 March 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate6 July 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate26 February 2027Closure · Not startedClosure · Not started
Team & roles
2 members, about 0.6 full-time equivalents
Leadership
2 members
- Eng. Mishari K. Al-OtaibiProject manager45%Allocated 105% across all projectsA
- Eng. Bandar M. Al-ShammariProject sponsor15%Allocated 105% across all projectsR
A AccountableR ResponsibleC ConsultedI Informed
Stakeholders
6 stakeholders, 4 of them below the engagement needed
Power / interest matrix
Pick one to see how they are handled
Keep satisfied1
high power, lower interest
Manage closely4
high power and interest
Monitor0
minimal effort
Keep informed1
high interest, lower power
Interest
Project sponsor
Eng. Turki A. Al-Anazi
Decisions and funding
Influence
Interest
Engagement level
Unaware
Resistant
Neutral
Supportive
Leading
A gap of 1 step — needs an engagement plan.
- Impact on the project
- Approves gates and changes
- Engagement plan
- Monthly briefing
Display options
| Organisation | Role | Actions | ||||||
|---|---|---|---|---|---|---|---|---|
| Eng. Turki A. Al-Anazi | Project sponsor | Decisions and funding | SupportiveLeading | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@sca.sa | 2026-10-20 | |||
| Eng. Bandar M. Al-Shammari | Project owner | Accepts deliverables, owns benefits | NeutralLeading | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@sca.sa | 2026-10-23 | |||
| Project Management Office (PMO) | Governance | Compliance and data quality | Supportive | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@sca.sa | 2026-10-17 | |||
| General Directorate of Financial Affairs | Internal department | Payment approval | NeutralSupportive | Haifa S. Al-RuwailiHaifa S. Al-RuwailiSenior Financial AnalystP-037h.alruwaili@sca.sa | 2026-10-14 | |||
| Sustainable Energy Contracting Est. | Main vendor | Delivers the contracted work | Supportive | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@sca.sa | 2026-10-24 | |||
| End beneficiaries | Beneficiaries | Users of the outcome | NeutralSupportive | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@sca.sa | 2026-09-26 |
Communication plan
Who needs what, when, through which channel, and who owns it.
- Project sponsorStatus and decisions neededMonthlyMeetingEng. Mishari K. Al-Otaibi2026-11-15
- Project ownerDeliverable status and acceptance datesFortnightlyEmailEng. Mishari K. Al-Otaibi2026-11-03
- PMOData and indicator updatesWeeklyDashboardEng. Mishari K. Al-Otaibi2026-10-31
- BeneficiariesWhat changes and whenAt milestonesNewsletterEng. Mishari K. Al-OtaibiAt launch
Coming up
By date
- 312026-10PMODashboard · Weekly
- 032026-11Project ownerEmail · Fortnightly
- 152026-11Project sponsorMeeting · Monthly