A late Dammam complex holds up the rehab specification and pushes Al-Jouf into summer 2027
PRK-09-1·Mitigate·Eng. Mishari K. Al-Otaibi
Programme · PG-09 · Building Rehabilitation & Sustainability Portfolio
Rehabilitating the Al-Khobar branch and the Al-Jouf and Khamis Mushait centres, solar power and energy efficiency.
incl. SAR 15M programme reserve
71% of budget
Estimate at completion
Planned 61%
Cost performance index 0.90
Manager
Eng. Mishari K. Al-Otaibi
Director, Sustainability & Energy Efficiency
Sponsor
Eng. Bandar M. Al-Shammari
Director General, Facilities & Premises
Projects
5 projects
2024-01-14 — 2027-10-31
On track 3Critical 1On hold 1
What the programme must achieve, and the strategic objectives it serves.
Bring 55% of existing branches and centres up to safety and efficiency standards
15% of SCA building energy from renewables
Cut SCA building emissions 12% from baseline
Serves strategic objectives
From baseline to target
Existing branches and centres rehabilitated
by 2027Renewable energy share
by 2026Energy-bill savings
by 2027One lane per project: start to forecast finish, with the progress earned and the baseline finish.
What waits on what. Red links are on the programme’s critical path.
Critical path
Critical
The Al-Jouf rehab applies the standard rehabilitation specification approved in Dammam
Lessons from the Abha fire and alarm works are applied in Al-Jouf
The retrofit builds on the solar metering in SCA buildings
Risks that hit more than one project, managed at programme level.
A late Dammam complex holds up the rehab specification and pushes Al-Jouf into summer 2027
PRK-09-1·Mitigate·Eng. Mishari K. Al-Otaibi
5 risks
Impact
| Probability \ Impact | 1 | 2 | 3 | 4 | 5 |
|---|---|---|---|---|---|
| 5 | 0 · Low | 0 · Medium | 0 · High | 0 · Critical | 1 · Critical |
| 4 | 0 · Low | 0 · Medium | 0 · Medium | 1 · High | 0 · Critical |
| 3 | 0 · Low | 0 · Low | 0 · Medium | 1 · Medium | 1 · High |
| 2 | 0 · Low | 0 · Low | 1 · Low | 0 · Medium | 0 · Medium |
| 1 | 0 · Low | 0 · Low | 0 · Low | 0 · Low | 0 · Low |
Carbon emissions cut across SCA buildings
9.7%
+1
Target 12.0%81%
Renewable share of SCA building energy
14.1%
+1
Target 15.0%94%
SCA centres operating in owned buildings
43%
0
Target 55%78%
Skills tests held per month
4.1thousand tests
0
Target 4.591%
Power against interest; click a person to see their role.
Keep satisfied1
Manage closely3
Monitor0
Keep informed0
Interest
What the committees decided on the programme’s projects, and what the programme raised to them.
ESCO energy retrofit put on hold pending funding
Executive Committee · 2026-10-06 · DEC-2026-035
Solar for SCA buildings passes the mid-execution review
Project Approval Committee · 2026-09-30 · DEC-2026-034
Task force formed for the Al-Khobar branch contractor distress
Executive Committee · 2026-09-22 · DEC-2026-032
Committees
Monthly · Quorum 5
Members
6 members
Weekly · Quorum 4
The programme’s performance is computed from these projects.
Display options
| Manager | ||||||||
|---|---|---|---|---|---|---|---|---|
| Al-Khobar Branch — Rehabilitation & ExtensionPRJ-2026-004 | Eng. Waleed O. Al-Juhani | 4Execution | Critical | 68% | 412M | 490.5M+19.0% | 0.74Schedule performance index · 0.74 | 0.84Cost performance index · 0.84 |
| Solar Power for SCA Buildings & CentresPRJ-2026-010 | Eng. Mishari K. Al-Otaibi | 4Execution | On track | 58% | 96M | 95.1M−1.0% | 1.02Schedule performance index · 1.02 | 1.01Cost performance index · 1.01 |
| Al-Jouf Training Centre RehabilitationPRJ-2026-025 | Eng. Mishari K. Al-Otaibi | 4Execution | On track | 36% | 42M | 41.2M−2.0% | 1.03Schedule performance index · 1.03 | 1.02Cost performance index · 1.02 |
| Energy Retrofit of Existing SCA Buildings (ESCO)PRJ-2026-026 | Eng. Mishari K. Al-Otaibi | 3Planning | On hold | 8% | 33M | 33M0.0% | 0.89Schedule performance index · 0.89 | 1.00Cost performance index · 1.00 |
| Khamis Mushait Training Centre RehabilitationPRJ-2026-036 | Eng. Waleed O. Al-Juhani | 5Closure | On track | 97% | 67M | 66.3M−1.0% | 0.98Schedule performance index · 0.98 | 1.01Cost performance index · 1.01 |
| Total · 5 | 650M | 726M |
SAR 650M
Budget
| Category | Value | Share |
|---|---|---|
| Al-Khobar Branch — Rehabilitation & Extension | SAR 412M | 63% |
| Solar Power for SCA Buildings & Centres | SAR 96M | 15% |
| Al-Jouf Training Centre Rehabilitation | SAR 42M | 6% |
| Energy Retrofit of Existing SCA Buildings (ESCO) | SAR 33M | 5% |
| Khamis Mushait Training Centre Rehabilitation | SAR 67M | 10% |
| Total | SAR 650M | 100% |