Solar Power for SCA Buildings & Centres
Add to watchlist6 MW of rooftop and carport solar across 14 SCA buildings and centres, the largest a ground array at the Tabuk site.
Budget (BAC)
Actual cost
57% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ExecutionStage 4 of 5
Next gate:Closure26 February 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate1 January 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate2 March 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate6 July 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate26 February 2027Closure · Not startedClosure · Not started
Scope statementRequired at this stage
What the project delivers, what it does not, and when a deliverable counts as accepted.
6 MW of rooftop and carport solar across 14 SCA buildings and centres, the largest a ground array at the Tabuk site.
In scope
- 6 MW of rooftop and carport solar across 14 SCA buildings and centres, the largest a ground array at the Tabuk site.
- Saudi Building Code compliance
- An approved plan to keep contractor services and training running during the works
Out of scope
- Operation and maintenance after the warranty period
- Work outside the approved site or system boundary
Acceptance criteria
- Main deliverable — stage 1Meets the approved specification, signed off by the project owner
- Main deliverable — final stageMeets the approved specification, signed off by the project owner
Scope baselineRequired at this stage
Every approved change creates a new baseline
- 1
SB-1Current2025-04-09
Baseline approved at the planning gate
Budget96MFinish2027-04-30
Requirements registerRequired at this stage
6 requirements of five kinds, with the trace status of each
By type
- Business1
- Functional1
- Technical1
- Regulatory2
- Security1
Fully traced
100%
6/6 · linked to a deliverable, task and test
Test passed
33%
2/6 · test result is a pass
Accepted
33%
2/6 · signed off by the business owner
Display options
| REQ-010-01 | Reach the target number of training & test halls | Business | Must | In progress | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.sa | SB-1 | |
| REQ-010-02 | Meet the approved technical specs | Technical | Must | Approved | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@sca.sa | SB-1 | |
| REQ-010-03 | Training and contractor service continue during the works | Functional | Must | In progress | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.sa | SB-1 | |
| REQ-010-04 | Saudi Building Code | Regulatory | Should | In progress | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@sca.sa | SB-1 | |
| REQ-010-05 | Civil-defence requirements | Regulatory | Should | In progress | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.sa | SB-1 | |
| REQ-010-06 | Site and systems security | Security | Could | Approved | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@sca.sa | SB-1 |
Traceability matrixRequired at this stage
Requirement → deliverable → task → test → acceptance. No requirement has a gap.