PRJ-2026-010On track4ExecutionConstruction

Solar Power for SCA Buildings & Centres

Add to watchlist

6 MW of rooftop and carport solar across 14 SCA buildings and centres, the largest a ground array at the Tabuk site.

Budget (BAC)

SAR 96M

Actual cost

SAR 55.1M

⁦57%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 95.1M

SPI · CPI

1.02Schedule performance index · 1.021.01Cost performance index · 1.01

Forecast finish

⁦2027-04-22⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure26 February 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate1 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate2 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate6 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate26 February 2027Closure · Not startedClosure · Not started

Project management plan

One plan bringing the schedule, deliverables, risks, communications, quality and benefits together from the project’s records, approved through the plan’s chain.

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Project management plan

Schedule, deliverables, risks, communications, quality and benefits

Form no.
SCA-PMO-F05
Template edition
2.0
Version
V2
Form date
⁦2025-03-27⁩
Hijri
27 Ramadan 1446 AH
ApprovedPRJ-2026-010Solar Power for SCA Buildings & Centres

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-010
Project
Solar Power for SCA Buildings & Centres
Portfolio
Building Rehabilitation & Sustainability Portfolio
Sector
Corporate Support Sector
Sponsor
Eng. Turki A. Al-Anazi
Project manager
Eng. Mishari K. Al-Otaibi

1ScheduleAuto-filled

From the project schedule and its approved baseline.

Start

⁦2025-03-02⁩

Baseline finish

⁦2027-04-30⁩

Forecast finish

⁦2027-04-22⁩

SPI

1.02

MilestonePlannedForecastSlip
Project plan approved⁦2025-08-12⁩⁦2025-09-25⁩+44 days
Designs approved⁦2025-12-15⁩⁦2026-03-03⁩+78 days
Build complete⁦2026-06-21⁩⁦2026-10-26⁩+127 days
Testing & acceptance complete⁦2026-12-26⁩⁦2027-03-05⁩+69 days
Final handover⁦2027-04-30⁩⁦2027-04-30⁩0

2DeliverablesAuto-filled

DeliverableWeightDueOwner
Project plan & baseline⁦3%⁩⁦2025-06-10⁩Eng. Mishari K. Al-Otaibi
Monitoring & reporting⁦3%⁩⁦2025-08-12⁩Eng. Bandar M. Al-Shammari
Detailed design⁦7%⁩⁦2025-10-13⁩Eng. Bandar M. Al-Shammari
Permits & approvals⁦6%⁩⁦2025-12-15⁩Eng. Turki A. Al-Anazi
Site works & excavation⁦13%⁩⁦2026-02-16⁩Eng. Turki A. Al-Anazi
Structure⁦13%⁩⁦2026-04-19⁩Eng. Mishari K. Al-Otaibi
Finishes⁦13%⁩⁦2026-06-21⁩Eng. Bandar M. Al-Shammari
Supply⁦10%⁩⁦2026-08-23⁩Eng. Mishari K. Al-Otaibi
Installation⁦9%⁩⁦2026-10-24⁩Eng. Bandar M. Al-Shammari
Testing & commissioning⁦9%⁩⁦2026-12-26⁩Eng. Turki A. Al-Anazi
Provisional acceptance⁦7%⁩⁦2027-02-26⁩Eng. Bandar M. Al-Shammari
Final acceptance⁦7%⁩⁦2027-04-30⁩Eng. Turki A. Al-Anazi
Accepted with a certificate⁦58%⁩——

3RisksAuto-filled

CodeRiskScoreResponseOwner
RSK-0041Falling global panel prices allow more capacity within budget12AcceptEng. Mishari K. Al-Otaibi

4CommunicationsAuto-filled

AudienceNeedFrequencyOwner
Project sponsorStatus and decisions neededMonthlyEng. Mishari K. Al-Otaibi
Project ownerDeliverable status and acceptance datesFortnightlyEng. Mishari K. Al-Otaibi
PMOData and indicator updatesWeeklyEng. Mishari K. Al-Otaibi
BeneficiariesWhat changes and whenAt each milestoneEng. Mishari K. Al-Otaibi
Team memberRoleAllocation
Eng. Mishari K. Al-OtaibiProject manager⁦45%⁩
Eng. Bandar M. Al-ShammariProject sponsor⁦15%⁩

5QualityAuto-filled

Quality leadAuto-filled
Eng. Mishari K. Al-Otaibi
Review cadenceAuto-filled
A flash test on a sample of each panel batch
Next reviewAuto-filled
⁦2026-11-09⁩
Quality criterionThresholdNowMet
Actual panel output≥ 97% of rated output94.8% in batch 6No
Performance ratio of live plants80% or more83%Yes

6BenefitsAuto-filled

BenefitBaselineTargetOwner
Solar energy generated0 MWh / year31000 MWh / yearEng. Mishari K. Al-Otaibi
Electricity bill savings0 SAR M9.3 SAR MHaifa S. Al-Ruwaili

Approval logChain: Project management plan approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencySubmitted—⁦2025-03-27⁩ 11:26
2Methodology review — PMOMethodology reviewGhada A. Al-ShahraniPMO — analystApprovedComplete against the project management plan template.⁦2025-03-31⁩ 13:58
3Technical acceptance — project ownerTechnical acceptanceEng. Bandar M. Al-ShammariProject ownerApproved—⁦2025-04-03⁩ 14:05
4Cash flow & financial commitmentFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2025-04-07⁩ 12:21
5Plan aligned with the contractsFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2025-04-08⁩ 13:58
6Sponsor approvalTechnical acceptanceEng. Turki A. Al-AnaziProject sponsorApproved—⁦2025-04-13⁩ 11:26

Signatures

Methodology review — PMO

Ghada A. Al-Shahrani

Approved⁦2025-03-31⁩

Technical acceptance — project owner

Eng. Bandar M. Al-Shammari

Approved⁦2025-04-03⁩

Cash flow & financial commitment

Munirah A. Al-Khalidi

Approved⁦2025-04-07⁩

Plan aligned with the contracts

Mazen A. Al-Hazmi

Approved⁦2025-04-08⁩

Sponsor approval

Eng. Turki A. Al-Anazi

Approved⁦2025-04-13⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F05 · version V2

Project management plan

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project management plan approval · version ⁦1⁩

Submitted by Eng. Mishari K. Al-Otaibi on ⁦2025-03-27⁩

  1. Methodology review

    Methodology review — PMO

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-03-31⁩ at ⁦13:58⁩

    Complete against the project management plan template.

  2. Technical acceptance

    Technical acceptance — project owner

    Eng. Bandar M. Al-Shammari · Project owner

    Approved · ⁦2025-04-03⁩ at ⁦14:05⁩

  3. Financial approval

    Cash flow & financial commitment

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2025-04-07⁩ at ⁦12:21⁩

  4. Financial approval

    Plan aligned with the contracts

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2025-04-08⁩ at ⁦13:58⁩

  5. Technical acceptance

    Sponsor approval

    Eng. Turki A. Al-Anazi · Project sponsor

    Approved · ⁦2025-04-13⁩ at ⁦11:26⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-03-27⁩

    Approved with the baseline

    • Schedule and cost baseline approved

    Eng. Mishari K. Al-Otaibi

  2. V1Returned for edit⁦2025-03-13⁩

    First draft — returned to complete the quality plan

    • Plan from the methodology template

    Eng. Mishari K. Al-Otaibi

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close