PRJ-2026-025On track4ExecutionConstruction

Al-Jouf Training Centre Rehabilitation

Add to watchlist

Rehabilitating the training centre building in Sakaka — halls, MEP systems and accessible entrances.

Budget (BAC)

SAR 42M

Actual cost

SAR 14.8M

⁦35%⁩ of budget

Progress

⁦36%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SAR 41.2M

SPI · CPI

1.03Schedule performance index · 1.031.02Cost performance index · 1.02

Forecast finish

⁦2027-09-30⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure4 August 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate13 August 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate12 October 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 February 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate4 August 2027Closure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

+1

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is close to plan: ⁦36%⁩ done against ⁦35%⁩ planned.

SPI ⁦1.03⁩, CPI ⁦1.02⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: Specialised, Value-adding ServicesSO-3.2Efficient, sustainable SCA facilities

Main initiative

SI-3.3.2Al-Jouf centre rehabilitation

Contribution to the initiative⁦100%⁩

The project’s share of the initiative’s project budget (1 project)

Annual work-plan line
WP-2025-025
Classification
Operational

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦36%⁩

Awaiting acceptance ⁦12%⁩

Not handed in ⁦52%⁩

5 deliverables accepted

  • Site works & excavation⁦15%⁩
  • Detailed design⁦7%⁩
  • Permits & approvals⁦7%⁩
  • Project plan & baseline⁦4%⁩
  • Monitoring & reporting⁦3%⁩

1 deliverable under inspection or acceptance

  • Structure⁦12%⁩

Progress & earned value

⁦3⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦86%⁩ of budget

14.8M/ 42M824Kprojected saving(⁦2.0%⁩)
Actual spend
14.8M
Committed
36M
Approved budget
42M
Estimate at completion
41.2M

Next milestones

  • Provisional acceptance⁦2027-08-04⁩On track
  • Closure⁦2027-09-30⁩On track

Waiting on someone

⁦0⁩ approvals and ⁦0⁩ open actions on this project

Approvals & requests

From «My actions» for this project

  • No approvals pending

Actions

⁦0⁩ open

  • No actions on this project

Change requests

Cost and schedule impact

  • No change requests

Risks & impediments

0 open risks, exposure SAR 0

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High0
  • Medium0
  • Low0

Top risks

  • No open risks

Open impediments

⁦0⁩ escalated

  • No open impediments

Deliverables

⁦5⁩ of ⁦12⁩ approved

  • Project plan & baseline025-D1 · V1 · CRT-025-01⁦4%⁩Eng. Mishari K. Al-Otaibi⁦2026-01-11⁩2026-01-1122 Rajab 1447 AHApproved
  • Monitoring & reporting025-D2 · V1 · CRT-025-02⁦3%⁩Eng. Bandar M. Al-Shammari⁦2026-03-09⁩2026-03-0920 Ramadan 1447 AHApproved
  • Detailed design025-D3 · V1 · CRT-025-03⁦7%⁩Eng. Bandar M. Al-Shammari⁦2026-05-05⁩2026-05-0518 Dhuʻl-Qiʻdah 1447 AHApproved
  • Permits & approvals025-D4 · V1 · CRT-025-04⁦7%⁩Eng. Turki A. Al-Anazi⁦2026-07-01⁩2026-07-0116 Muharram 1448 AHApproved
  • Site works & excavation025-D5 · V1 · CRT-025-05⁦15%⁩Eng. Turki A. Al-Anazi⁦2026-08-27⁩2026-08-2714 Rabiʻ I 1448 AHApproved
  • Structure025-D6 · V1⁦12%⁩Eng. Mishari K. Al-Otaibi5 days overdue2026-10-2312 Jumada I 1448 AHSubmitted
  • Finishes025-D7 · V0⁦12%⁩Eng. Bandar M. Al-ShammariIn 52 days2026-12-1910 Rajab 1448 AHDraft
  • Supply025-D8 · V0⁦9%⁩Eng. Mishari K. Al-OtaibiIn 109 days2027-02-147 Ramadan 1448 AHDraft
  • Installation025-D9 · V0⁦9%⁩Eng. Bandar M. Al-ShammariIn 166 days2027-04-125 Dhuʻl-Qiʻdah 1448 AHDraft
  • Testing & commissioning025-D10 · V0⁦9%⁩Eng. Turki A. Al-AnaziIn 223 days2027-06-083 Muharram 1449 AHDraft
  • Provisional acceptance025-D11 · V0⁦7%⁩Eng. Bandar M. Al-ShammariIn 280 days2027-08-042 Rabiʻ I 1449 AHDraft
  • Final acceptance025-D12 · V0⁦6%⁩Eng. Turki A. Al-AnaziIn 337 days2027-09-3029 Rabiʻ II 1449 AHDraft

Team, contracts & documents

Team

2 members

Eng. Mishari K. Al-Otaibi · Director, Sustainability & Energy EfficiencyEng. Bandar M. Al-Shammari · Director General, Facilities & Premises
  • Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyProject managerP-028m.alotaibi@sca.sa⁦45%⁩
  • Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesProject sponsorP-013b.alshammari@sca.sa⁦15%⁩

Documents

  • No documents yet

Meetings

  • No meetings scheduled
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close