PRJ-2026-025On track4ExecutionConstruction
Al-Jouf Training Centre Rehabilitation
Add to watchlistRehabilitating the training centre building in Sakaka — halls, MEP systems and accessible entrances.
Project managerEng. Mishari K. Al-OtaibiProject sponsorEng. Turki A. Al-AnaziProgrammeBuilding Rehabilitation & Efficiency Programme
Budget (BAC)
SAR 42M
Actual cost
SAR 14.8M
35% of budget
Progress
36%Awaiting acceptance 12%
Estimate at completion
SAR 41.2M
SPI · CPI
1.03Schedule performance index · 1.031.02Cost performance index · 1.02
Forecast finish
2027-09-30
On baseline
ExecutionStage 4 of 5
Next gate:Closure4 August 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionConditional goDate13 August 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate12 October 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate4 February 2026Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate4 August 2027Closure · Not startedClosure · Not started
Periodic update cards
Filled by the project manager every period — progress, status, risks and support requested — prefilled from the previous card and the live data, then approved.
Periodic update cards
| Period | Status | Progress | Current step | Date |
|---|---|---|---|---|
| October 2026UPD-025-2026-10 | Draft | 36% | — | 2026-10-26 |
| September 2026UPD-025-2026-09 | Approved | 34% | — | 2026-10-02 |
| August 2026UPD-025-2026-08 | Approved | 32% | — | 2026-09-02 |