Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-025On track4ExecutionConstruction

Al-Jouf Training Centre Rehabilitation

Add to watchlist

Rehabilitating the training centre building in Sakaka — halls, MEP systems and accessible entrances.

Budget (BAC)

SAR 42M

Actual cost

SAR 14.8M

⁦35%⁩ of budget

Progress

⁦36%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SAR 41.2M

SPI · CPI

1.03Schedule performance index · 1.031.02Cost performance index · 1.02

Forecast finish

⁦2027-09-30⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure4 August 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate13 August 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate12 October 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 February 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate4 August 2027Closure · Not startedClosure · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 42M split into spent, committed and left, with the estimate at completion

EAC SAR 41.2M
Revised request SAR 42M
  • Actual spendSAR 14.8M
  • Committed, not spentSAR 21.2M
  • Allotted, uncommittedSAR 4.7M
  • Contingency availableSAR 1.3M

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SAR 39.1M
Original budgetwhen the first baseline was approved
SAR 42M
Approved budgetafter approved change requests
SAR 42M
Current budgetavailable to spend now
SAR 42M
Revised budgetif the pending changes are approved
SAR 42M

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SAR 36M
Contracts1 active contract
SAR 33M
Purchase orders⁦2⁩ orders
SAR 3M
Remaining budgetapproved less actual
SAR 27.2M

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SAR 14.8M
Accrualswork done, not yet invoiced
SAR 593K
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SAR 41.2M
ContingencySAR 840K drawn of SAR 2.1M
SAR 1.3M

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSAR 39.1M
ApprovedSAR 42M
Estimate at completionSAR 41.2M
Approved is SAR 2.9M (⁦7.4%⁩) above the estimate
The estimate at completion is SAR 2.1M (⁦5.3%⁩) above the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2025-07-29⁩ · The gap between estimated and approved comes from the scope update and the change requests approved after the approval gate.

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-71025
  • WBS elements⁦5⁩ elements · P-2026-025.01 …
  • Purchase orders⁦2⁩ synced · ⁦0⁩ manual
  • Invoices & certificates⁦7⁩ posted · ⁦0⁩ in approval
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 840K drawn of SAR 2.1M

  • Covering realised delivery risks⁦2026-08-29⁩SAR 840K

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance2.442.472.472.47⁦−0.03⁩
2Design & permits4.894.944.944.94⁦−0.05⁩
3Civil works15.4813.987.4115.40⁦+0.09⁩
4MEP works12.229.960.0012.09⁦+0.13⁩
5Handover5.704.650.005.64⁦+0.06⁩
Unallocated contingency1.260.000.000.63⁦+0.63⁩
Total42.0036.0014.8241.18⁦+0.82⁩

Budget split

WBS

SAR 42M

Budget

  • Management & governanceSAR 2.4M⁦6%⁩
  • Design & permitsSAR 4.9M⁦12%⁩
  • Civil worksSAR 15.5M⁦37%⁩
  • MEP worksSAR 12.2M⁦29%⁩
  • HandoverSAR 5.7M⁦14%⁩
  • Unallocated contingencySAR 1.3M⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative
  • Forecast

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2028-05-28⁩+241

SPI(t) ⁦0.75⁩ against the approved finish ⁦2027-09-30⁩

Planned valuePV
SAR 23.6M
The value of the work that should be done by today.
PV
Earned valueEV
SAR 15.1M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 14.8M
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 42M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦+0.30⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−8.50⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
1.02
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.64
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 41.2M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 26.4M
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦+0.82⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
0.99
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 41.2M
  • If the rest goes to planSAR 41.7M
  • At cost and schedule performanceSAR 56M
  • The PM’s bottom-up estimateSAR 41.2M
  • The performance needed on the rest is below what has been achieved; the budget holds.

Estimate at completion at that performance

SAR 41.2M

Variance at completion: ⁦+0.82⁩ SAR M

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close