PRJ-2026-036On track5ClosureConstruction

Khamis Mushait Training Centre Rehabilitation

Add to watchlist

Rehabilitating the Khamis Mushait training centre — fire and alarm systems and training halls.

Budget (BAC)

SAR 67M

Actual cost

SAR 64.3M

⁦96%⁩ of budget

Progress

⁦97%⁩Awaiting acceptance ⁦3%⁩

Estimate at completion

SAR 66.3M

SPI · CPI

0.98Schedule performance index · 0.981.01Cost performance index · 1.01

Forecast finish

⁦2026-11-12⁩

12 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 August 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate6 October 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate4 February 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate1 September 2026Closure · Current stageClosure · Current stage

Project documents by stage

What each stage requires under the RFP, what has been filed and what is missing, and the evidence tied to deliverables.

Open in the repository
  • ⁦1⁩ of ⁦9⁩ mandatory documents due
  • 8 mandatory documents missing
  • 1 document in the repository

The project is in its closure stage

Once the closure & handover form is approved, the project’s documents move to the archive, read-only.

Stages and required documents

For each of the five stages, what its gates and forms require: present, missing, or not yet due.

  1. 1Pre-start
    • Project proposal & feasibility studyMandatory· Missing

      Approval gate G1

    • Priority & weight assessmentOptional· Missing

      Annual work plan

  2. 2Initiation
    • Approved project charterMandatory· Missing

      Initiation gate G2

    • Kick-off meeting minutesMandatory· Missing

      Initiation gate G2

  3. 3Planning
    • Project management plan, schedule & baselineMandatory· Missing

      Planning gate G3

    • Contract or purchase orderMandatory· Missing

      Finance & procurement — when there is a contract

    • Technical studies & drawingsOptional· Missing

      Project management plan

  4. 4Execution
    • Periodic update cards & status reportsMandatory· Missing

      Periodic update card form

    • Deliverable completion certificatesMandatory· Missing

      Deliverable completion certificate form

    • Corrective plan when off trackOptional· Missing

      Corrective plan form

  5. 5ClosureCurrent stage

Evidence tied to deliverables

Each deliverable with its repository document and the files that prove it.

  • 036-D1Project plan & baselinePRJ-2026-036_1.1_v1.pdfApprovedDeliverable
  • 036-D2Monitoring & reportingPRJ-2026-036_1.2_v1.pdfApprovedDeliverable
  • 036-D3Detailed designPRJ-2026-036_2.1_v1.pdfApprovedDeliverable
  • 036-D4Permits & approvalsPRJ-2026-036_2.2_v1.pdfApprovedDeliverable
  • 036-D5Site works & excavationPRJ-2026-036_3.1_v1.pdfApprovedDeliverable
  • 036-D6StructurePRJ-2026-036_3.2_v1.pdfApprovedDeliverable
  • 036-D7FinishesPRJ-2026-036_3.3_v1.pdfApprovedDeliverable
  • 036-D8SupplyPRJ-2026-036_4.1_v1.pdfApprovedDeliverable
  • 036-D9InstallationPRJ-2026-036_4.2_v1.pdfApprovedDeliverable
  • 036-D10Testing & commissioningPRJ-2026-036_4.3_v1.pdfApprovedDeliverable
  • 036-D11Provisional acceptancePRJ-2026-036_5.1_v1.pdfApprovedDeliverable
  • 036-D12Final acceptancePRJ-2026-036_5.2_v1.pdfIn reviewDeliverable