PRJ-2026-036On track5ClosureConstruction

Khamis Mushait Training Centre Rehabilitation

Add to watchlist

Rehabilitating the Khamis Mushait training centre — fire and alarm systems and training halls.

Budget (BAC)

SAR 67M

Actual cost

SAR 64.3M

⁦96%⁩ of budget

Progress

⁦97%⁩Awaiting acceptance ⁦3%⁩

Estimate at completion

SAR 66.3M

SPI · CPI

0.98Schedule performance index · 0.981.01Cost performance index · 1.01

Forecast finish

⁦2026-11-12⁩

12 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 August 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate6 October 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate4 February 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate1 September 2026Closure · Current stageClosure · Current stage
Fields required by the project’s stage (Closure): 15 fields required now.Field settings

Saudi Contractors Authority

Project charter

Khamis Mushait Training Centre Rehabilitation

APPROVEDV2Approved ⁦2024-10-04⁩

1Project identity

Required at this stage
Project name
Khamis Mushait Training Centre Rehabilitation
Project code
PRJ-2026-036
Project sponsor
Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.sa
Project manager
Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@sca.sa
Project owner
Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.sa
Portfolio & programme
Building Rehabilitation & Sustainability PortfolioBuilding Rehabilitation & Efficiency Programme
Type & methodology
Infrastructure · Construction
Current phase
5Closure

2Background & rationale

Required at this stage

Rehabilitating the Khamis Mushait training centre — fire and alarm systems and training halls.

3Objectives

Required at this stage
  1. 1Efficient, sustainable SCA facilities
Serves the strategic objectives:SO-3.2Efficient, sustainable SCA facilities

4Scope

Required at this stage

In scope

  • Rehabilitating the Khamis Mushait training centre — fire and alarm systems and training halls.
  • Saudi Building Code compliance
  • An approved plan to keep contractor services and training running during the works

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

Required at this stage
  1. 1Saudi Building Code compliance
  2. 2An approved plan to keep contractor services and training running during the works
  3. 3Civil-defence requirements

6Deliverables

Required at this stage
1Project management plan⁦2024-11-05⁩
2Main deliverable — stage 1⁦2025-10-26⁩
3Main deliverable — final stage⁦2026-07-17⁩
4Final report⁦2026-10-31⁩

7Key milestones

Required at this stage
  1. Charter approved⁦2024-10-04⁩
  2. Contract signed⁦2025-02-04⁩
  3. 50% of works complete⁦2025-10-26⁩
  4. Provisional acceptance⁦2026-09-01⁩
  5. Closure⁦2026-10-31⁩

8Budget

Required at this stage
  • Main contract⁦71.9%⁩48.2M
  • Supervision & consulting⁦14.0%⁩9.4M
  • Internal team⁦9.0%⁩6M
  • Contingency reserve (⁦5%⁩)⁦5.1%⁩3.4M
The owning sector’s approved budgetTotal67M

9Timeline

Required at this stage
Start
2024-10-063 Rabiʻ II 1446 AH
Baseline finish
2026-10-3120 Jumada I 1448 AH
Duration
⁦25⁩ months

10Key risks

Required at this stage
  • LowPreliminary-handover snags on the fire and alarm systems

11Constraints

Required at this stage
  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

12Assumptions

Required at this stage
  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

13Stakeholders

Required at this stage
  • Project sponsorDecisions and funding
  • Project ownerAccepts deliverables, owns benefits
  • Project Management Office (PMO)Governance and compliance

14Success criteria

Required at this stage
  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3Target benefits within ⁦12⁩ months

15Governance structure

Required at this stage
  • Change Control BoardApproves scope, cost and schedule changesWeekly
  • PMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly