0.98Schedule performance index · 0.981.01Cost performance index · 1.01
Forecast finish
2026-11-12
12 days behind baseline
Closure·Stage 5 of 5
Pre-start · CompletePre-start · Complete
Gate into «Initiation»DecisionGoDate7 August 2024Initiation · CompleteInitiation · Complete
Gate into «Planning»DecisionGoDate6 October 2024Planning · CompletePlanning · Complete
Gate into «Execution»DecisionConditional goDate4 February 2025Execution · CompleteExecution · Complete
Gate into «Closure»DecisionGoDate1 September 2026Closure · Current stageClosure · Current stage
Risks, assumptions, impediments & dependencies
Risks, assumptions, impediments and dependencies in one log for the project — what may happen, what we assume, what has happened, and what we wait on from others.