PRJ-2026-036On track5ClosureConstruction
Khamis Mushait Training Centre Rehabilitation
Add to watchlistRehabilitating the Khamis Mushait training centre — fire and alarm systems and training halls.
Project managerEng. Waleed O. Al-JuhaniProject sponsorEng. Turki A. Al-AnaziProgrammeBuilding Rehabilitation & Efficiency Programme
Budget (BAC)
SAR 67M
Actual cost
SAR 64.3M
96% of budget
Progress
97%Awaiting acceptance 3%
Estimate at completion
SAR 66.3M
SPI · CPI
0.98Schedule performance index · 0.981.01Cost performance index · 1.01
Forecast finish
2026-11-12
12 days behind baseline
ClosureStage 5 of 5
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate7 August 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate6 October 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionConditional goDate4 February 2025Execution · CompleteExecution · Complete
- Gate into «Closure»DecisionGoDate1 September 2026Closure · Current stageClosure · Current stage
Periodic update cards
Filled by the project manager every period — progress, status, risks and support requested — prefilled from the previous card and the live data, then approved.
Periodic update cards
No update cards for this project — they start with execution.