0.98Schedule performance index · 0.981.01Cost performance index · 1.01
Forecast finish
2026-11-12
12 days behind baseline
Closure·Stage 5 of 5
Pre-start · CompletePre-start · Complete
Gate into «Initiation»DecisionGoDate7 August 2024Initiation · CompleteInitiation · Complete
Gate into «Planning»DecisionGoDate6 October 2024Planning · CompletePlanning · Complete
Gate into «Execution»DecisionConditional goDate4 February 2025Execution · CompleteExecution · Complete
Gate into «Closure»DecisionGoDate1 September 2026Closure · Current stageClosure · Current stage
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Finish-date drift
+38 days vs approved
Baseline (original = approved)2026-10-31
Current forecast2026-12-08
By earned schedule2027-01-25
Critical activities
2
of 2 open activities
Late activities
1
past their baseline finish
Schedule performance
0.97
earned ÷ planned value
Next milestone
in 41 days
Final handover
Layers
Compare with
Expand allCollapse all
ActivityOwnerForecast finishProgress
2024
2025
2026
2027
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Today
2026-12-0897%
Khamis Mushait Training Centre RehabilitationPlanned: 2024-10-06 → 2026-10-31Forecast: 2024-10-06 → 2026-12-08Float: 0d