RSK-0043Energy Retrofit of Existing SCA Buildings (ESCO)

Funding left out of the 2027 budget, keeping the tender suspended

16HighEscalatedMaterial

A risk's detail, response, contingency and residual risk.

Latest escalation · ESC-2026-012

Executive committee

Energy-retrofit funding is missing from the draft 2027 budget and the tender stays suspended

FundingSAR 4.8M· Asked from: Executive Committee

Put SAR 4.8M into the 2027 budget, or approve an ESCO funding model

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

The initiative is not in the draft 2027 budget; the headquarters and qualification-centre projects took priority

Preventive controls

  • Present an ESCO funding model with no capital budget

1 / 1

Event

Funding left out of the 2027 budget, keeping the tender suspended

16HighTrigger

The 2027 budget approved without the initiative

Contingency

Pilot on two buildings from the operating budget

Impact

The tender stays suspended and about SAR 4.8M of yearly energy savings in SCA buildings is lost

SAR 4.8M

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
16High

Residual

5
4
3
2
1
1
2
3
4
5
9Medium

Exposure

SAR 4.8M

Residual

⁦44⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director

Last reviewed 20 days ago

  1. Project manager

    Eng. Mishari K. Al-Otaibi

    Currently followed up here
  2. Programme manager

    Eng. Mishari K. Al-Otaibi

    Automatically at 15 days unreviewed · threshold passed 5 days ago
  3. PMO director

    Current level

    Dr. Noura M. Al-Otaibi

    Automatically at 20 days unreviewed · threshold passed 0 days ago
  4. 4

    Executive committee

    Dr. Abdullah S. Al-Qahtani

    By the PMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦0⁩ of ⁦1⁩ done
  • Present an ESCO funding model with no capital budget

    Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@sca.sa
    In progressIn 23 days2026-11-2010 Jumada II 1448 AH

Trigger

The 2027 budget approved without the initiative

Contingency

Pilot on two buildings from the operating budget

Esc