RSK-0021Al-Khobar Branch — Rehabilitation & Extension

Main contractor cash-flow distress and unpaid subcontractors

25CriticalEscalatedMaterial

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

Late payment of earlier certificates and weak finances at the main contractor

Preventive controls

  • An executive task force on the contractor’s distress
  • Pay critical subcontractors directly with the contractor’s consent
  • Fast-track certificate 33

2 / 3

Event

Main contractor cash-flow distress and unpaid subcontractors

25CriticalTrigger

Site work stopped for more than 7 consecutive days

Contingency

Take part of the works away and give it to a second contractor under the contract

Impact

Subcontractors and labour idle, commissioning more than four months late, and the Eastern & Northern branch and its training halls still in a leased building

SAR 36M

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
25Critical

Residual

5
4
3
2
1
1
2
3
4
5
12Medium

Exposure

SAR 36M

Residual

⁦52⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director

Last reviewed 1 day ago

  1. Project manager

    Eng. Waleed O. Al-Juhani

    Currently followed up here
  2. Programme manager

    Current level

    Eng. Mishari K. Al-Otaibi

    Automatically at 15 days unreviewed · in 14 days
  3. 3

    PMO director

    Dr. Noura M. Al-Otaibi

    Automatically at 20 days unreviewed · in 19 days
  4. 4

    Executive committee

    Dr. Abdullah S. Al-Qahtani

    By the PMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦1⁩ of ⁦3⁩ done
  • An executive task force on the contractor’s distress

    Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.sa
    Done⁦2026-09-22⁩2026-09-2211 Rabiʻ II 1448 AH
  • Pay critical subcontractors directly with the contractor’s consent

    Khalid N. Al-MutairiKhalid N. Al-MutairiSenior Finance & Procurement SpecialistP-007k.almutairi@sca.sa
    In progressIn 8 days2026-11-0525 Jumada I 1448 AH
  • Fast-track certificate 33

    Khalid N. Al-MutairiKhalid N. Al-MutairiSenior Finance & Procurement SpecialistP-007k.almutairi@sca.sa
    Overdue3 days overdue2026-10-2514 Jumada I 1448 AH

Trigger

Site work stopped for more than 7 consecutive days

Contingency

Take part of the works away and give it to a second contractor under the contract

Esc