Al-Khobar Branch — Rehabilitation & Extension
Remove from watchlistRebuilding the Eastern & Northern branch office and adding a new wing with 28 training and skills-test halls.
Budget (BAC)
Actual cost
81% of budget
Progress
Estimate at completion
SAR +78.5M
SPI · CPI
Forecast finish
126 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure13 July 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate15 November 2023Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate14 January 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionConditional goDate20 June 2024Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate13 July 2026Closure · Not startedClosure · Not started