RSK-0022Al-Khobar Branch — Rehabilitation & Extension

Fire-fighting and evacuation systems failing Civil Defence requirements

15HighOpenMaterial

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

Drawings revised for the new training & test hall wing were never shown to Civil Defence, and evacuation rules are stricter for busy test halls

Preventive controls

  • An early review of the fire and evacuation drawings with Civil Defence
  • An integrated test of the alarm and fire systems before the official inspection

2 / 2

Event

Fire-fighting and evacuation systems failing Civil Defence requirements

15HighTrigger

Major findings at the Civil Defence inspection

Contingency

Open the rehabilitated existing building first and hold the new wing until it is approved

Impact

No safety certificate, so the branch cannot open to contractors and trainees

SAR 12M

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
15High

Residual

5
4
3
2
1
1
2
3
4
5
8Medium

Exposure

SAR 12M

Residual

⁦47⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director

Last reviewed 9 days ago

  1. Project manager

    Current level

    Eng. Waleed O. Al-Juhani

    Currently followed up here
  2. 2

    Programme manager

    Eng. Mishari K. Al-Otaibi

    Automatically at 15 days unreviewed · in 6 days
  3. 3

    PMO director

    Dr. Noura M. Al-Otaibi

    Automatically at 20 days unreviewed · in 11 days
  4. 4

    Executive committee

    Dr. Abdullah S. Al-Qahtani

    By the PMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦0⁩ of ⁦2⁩ done
  • An early review of the fire and evacuation drawings with Civil Defence

    Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@sca.sa
    In progressIn 18 days2026-11-155 Jumada II 1448 AH
  • An integrated test of the alarm and fire systems before the official inspection

    Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@sca.sa
    Not startedIn 53 days2026-12-2011 Rajab 1448 AH

Trigger

Major findings at the Civil Defence inspection

Contingency

Open the rehabilitated existing building first and hold the new wing until it is approved