RSK-0022Al-Khobar Branch — Rehabilitation & Extension
Fire-fighting and evacuation systems failing Civil Defence requirements
A risk's detail, response, contingency and residual risk.
Risk statement
From cause to event to impact — with the preventive controls before the event and the contingency after it
Cause
Drawings revised for the new training & test hall wing were never shown to Civil Defence, and evacuation rules are stricter for busy test halls
Preventive controls
- An early review of the fire and evacuation drawings with Civil Defence
- An integrated test of the alarm and fire systems before the official inspection
2 / 2
Event
Fire-fighting and evacuation systems failing Civil Defence requirements
Major findings at the Civil Defence inspection
Contingency
Open the rehabilitated existing building first and hold the new wing until it is approved
Impact
No safety certificate, so the branch cannot open to contractors and trainees
Assessment
The level before and after the response
Inherent
Residual
Exposure
SAR 12M
Residual
47% off the score
Score trend
Last six months
- Score
- Target residual
Escalation path
Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director
Last reviewed 9 days ago
Project manager
Current levelEng. Waleed O. Al-Juhani
Currently followed up here- 2
Programme manager
Eng. Mishari K. Al-Otaibi
Automatically at 15 days unreviewed · in 6 days - 3
PMO director
Dr. Noura M. Al-Otaibi
Automatically at 20 days unreviewed · in 11 days - 4
Executive committee
Dr. Abdullah S. Al-Qahtani
By the PMO director’s decision
Mitigation plan
Each action with its owner and date — tick it off when complete
An early review of the fire and evacuation drawings with Civil Defence
Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@sca.saIn progressIn 18 days2026-11-155 Jumada II 1448 AHAn integrated test of the alarm and fire systems before the official inspection
Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@sca.saNot startedIn 53 days2026-12-2011 Rajab 1448 AH
Trigger
Major findings at the Civil Defence inspection
Contingency
Open the rehabilitated existing building first and hold the new wing until it is approved