“United Buildings & Operations Co.” is 95 days late and it affects “Al-Khobar Branch — Rehabilitation & Extension” and “Hail Vocational Qualification Centre” and 1 more
Dependencies between projects, programmes and vendors, and knock-on delay.
across 36 items
beyond their float
half the float used
outside the Authority’s control
through delay propagation
When a party’s delay exceeds the float, it carries on to whatever depends on it — these are the chains that need action now
“United Buildings & Operations Co.” is 95 days late and it affects “Al-Khobar Branch — Rehabilitation & Extension” and “Hail Vocational Qualification Centre” and 1 more
“Saudi Electricity Company” is 75 days late and it affects “SCA Headquarters, Riyadh” and “Arar Vocational Qualification Centre” and 1 more
“Digital Platforms Solutions Co.” is 43 days late and it affects “Muqawil Platform — Release 4” and “Muqawil Mobile App — Release 3” and 1 more
“National Information Center (Nafath)” is 40 days late and it affects “Muqawil Platform — Release 4” and “Muqawil Mobile App — Release 3” and 1 more
Tasks, projects, programmes, vendors and external entities — hover an item to see what it depends on and what depends on it, click it for its details
Delay simulator
What if an item slips further? Pick it and a number of days to see how far the effect travels.
Extra delay30 days
Each dependency: who waits on whom, for what, by when, with how much float, and the delay it carries now
Display options
DEP-029 Commissioning passed before handover and the branch moves in | Branch systems commissioning (HVAC & fire)Task | Al-Khobar Branch — Rehabilitation & ExtensionProject | Finish-to-start | 2026-09-30 | 0 days | 126 days | 126 days | Late | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@sca.sa |
DEP-031 More training & testing capacity after rehabilitation | Al-Khobar Branch — Rehabilitation & ExtensionProject | Building Rehabilitation & Efficiency ProgrammeProgramme | Programme outcome | 2027-03-31 | 30 days | 126 days | 96 days | Late | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@sca.sa |
DEP-027 Electro-mechanical works complete | United Buildings & Operations Co.Vendor | Branch systems commissioning (HVAC & fire)Task | Deliverable | 2026-08-31 | 0 days | 95 days | 95 days | Late | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@sca.sa |
DEP-018 HV line diversion in zone 4 | Saudi Electricity CompanyExternal entity | SCA Headquarters, RiyadhProject | Service | 2026-09-30 | 0 days | 75 days | 75 days | Late | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020a.asiri@sca.sa |
DEP-021 HQ complete and the Authority’s sectors moved in | SCA Headquarters, RiyadhProject | Headquarters & Major Qualification Centres ProgrammeProgramme | Programme outcome | 2027-06-30 | 0 days | 75 days | 75 days | Late | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020a.asiri@sca.sa |
DEP-022 The Qassim vocational qualification centre in service | Qassim Vocational Qualification CentreProject | Headquarters & Major Qualification Centres ProgrammeProgramme | Programme outcome | 2027-05-31 | 0 days | 64 days | 64 days | Late | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020a.asiri@sca.sa |
DEP-016 Automated financial processes | SCA ERP SystemProject | Enterprise Systems & Government Integration ProgrammeProgramme | Programme outcome | 2026-12-31 | 0 days | 58 days | 58 days | Late | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@sca.sa |
DEP-019 Foundations complete before the concrete frame | Foundations of axes 12 to 16Task | Qassim Vocational Qualification CentreProject | Finish-to-start | 2026-12-15 | 0 days | 55 days | 55 days | Late | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020a.asiri@sca.sa |
DEP-020 The training & test hall and security standards approved at HQ | SCA Headquarters, RiyadhProject | Arar Vocational Qualification CentreProject | Finish-to-start | 2027-07-31 | 20 days | 75 days | 55 days | Late | Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@sca.sa |
DEP-003 Wave 1 contractor service package | Digital Platforms Solutions Co.Vendor | Wave 1 development (24 contractor services)Task | Deliverable | 2026-09-30 | 0 days | 43 days | 43 days | Late | Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, Muqawil Platform — Release 4P-005s.alghamdi@sca.sa |
DEP-006 UAT passed before the official launch | User acceptance testingTask | Muqawil Platform — Release 4Project | Finish-to-start | 2027-01-31 | 0 days | 42 days | 42 days | Late | Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, Muqawil Platform — Release 4P-005s.alghamdi@sca.sa |
DEP-011 Programme target: 85% of contractor services digital | Muqawil Platform — Release 4Project | Muqawil & e-Services ProgrammeProgramme | Programme outcome | 2027-03-31 | 0 days | 42 days | 42 days | Late | Eng. Reem K. Al-DosariEng. Reem K. Al-DosariHead of the Muqawil Platform & Programme Manager, Muqawil & e-ServicesP-004r.aldosari@sca.sa |
DEP-001 A dedicated Nafath test environment | National Information Center (Nafath)External entity | Nafath & Government Service Bus integration completeTask | Service | 2026-10-31 | 0 days | 40 days | 40 days | Late | Hussam T. Al-QurashiHussam T. Al-QurashiSenior Software Engineer – IntegrationP-030h.alqurashi@sca.sa |
DEP-005 Developed services ready for testing | Wave 1 development (24 contractor services)Task | User acceptance testingTask | Finish-to-start | 2026-12-01 | 4 days | 43 days | 39 days | Late | Joud N. Al-AhmadiJoud N. Al-AhmadiQA & Testing SpecialistP-033j.alahmadi@sca.sa |
DEP-010 Muqawil service APIs for the mobile app | Muqawil Platform — Release 4Project | Muqawil Mobile App — Release 3Project | Data | 2027-01-15 | 6 days | 42 days | 36 days | Late | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@sca.sa |
DEP-030 The standard e-test hall, proven in the Al-Khobar wing | Al-Khobar Branch — Rehabilitation & ExtensionProject | Hail Vocational Qualification CentreProject | Service | 2026-12-31 | 92 days | 126 days | 34 days | Late | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Regional Qualification CentresP-023f.alsulami@sca.sa |
DEP-004 UAT cannot start before integration is complete | Nafath & Government Service Bus integration completeTask | User acceptance testingTask | Finish-to-start | 2026-12-01 | 10 days | 40 days | 30 days | Late | Joud N. Al-AhmadiJoud N. Al-AhmadiQA & Testing SpecialistP-033j.alahmadi@sca.sa |
DEP-013 Etimad e-link certification | Etimad (Ministry of Finance)External entity | SCA ERP SystemProject | Service | 2026-10-31 | 0 days | 28 days | 28 days | Late | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@sca.sa |
DEP-015 Cost centres and digitisation contracts from the ERP | SCA ERP SystemProject | Mimar — Unified Building Journey & Government IntegrationProject | Data | 2027-03-01 | 30 days | 58 days | 28 days | Late | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@sca.sa |
DEP-023 Trenching permits for the network in the districts | Regional municipalities (trenching permits)External entity | Secure Enterprise NetworkProject | Approval | 2026-10-15 | 15 days | 40 days | 25 days | Late | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@sca.sa |
DEP-007 Disaster-recovery site for the Authority’s systems | SCA Backup Data CentreProject | SCA Systems Migration to the CloudProject | Service | 2026-12-31 | 14 days | 38 days | 24 days | Late | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@sca.sa |
DEP-002 Updated Government Service Bus interface specification | Government Service BusExternal entity | Nafath & Government Service Bus integration completeTask | Deliverable | 2026-10-20 | 25 days | 23 days | — | At risk | Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, Muqawil Platform — Release 4P-005s.alghamdi@sca.sa |
DEP-008 Production environment on the government cloud | SCA Systems Migration to the CloudProject | Muqawil Platform — Release 4Project | Service | 2027-01-31 | 30 days | 24 days | — | At risk | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@sca.sa |
DEP-009 UX standards compliance approval | Digital Government AuthorityExternal entity | Muqawil Platform — Release 4Project | Approval | 2027-02-15 | 10 days | 0 days | — | On track | Lama S. Al-HarbiLama S. Al-HarbiSenior Business Analyst — Contractor ServicesP-006l.alharbi@sca.sa |
DEP-012 The mobile channel in the programme KPIs | Muqawil Mobile App — Release 3Project | Muqawil & e-Services ProgrammeProgramme | Programme outcome | 2027-01-31 | 40 days | 36 days | — | At risk | Eng. Reem K. Al-DosariEng. Reem K. Al-DosariHead of the Muqawil Platform & Programme Manager, Muqawil & e-ServicesP-004r.aldosari@sca.sa |
DEP-014 Financial module customisations | Integrated Business Systems Co.Vendor | SCA ERP SystemProject | Deliverable | 2026-11-15 | 30 days | 21 days | — | At risk | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@sca.sa |
DEP-017 Data governance policies (gate condition) | Contracting Sector Information Centre & Data GovernanceProject | Project Tracking Platform — National PhaseProject | Approval | 2027-01-31 | 20 days | 18 days | — | At risk | Rahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & InnovationP-027r.alnefaie@sca.sa |
DEP-024 E-test halls linked to the secure enterprise network | Secure Enterprise NetworkProject | Electronic Skills-test Halls — Makkah RegionProject | Service | 2027-06-30 | 60 days | 33 days | — | At risk | Eng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@sca.sa |
DEP-025 Network for the unified operations centre | Secure Enterprise NetworkProject | Unified Operations Centre for Centres & PlatformsProject | Service | 2027-09-30 | 90 days | 33 days | — | On track | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@sca.sa |
DEP-026 SCA building and test-hall camera and gate feeds into the operations centre | Smart Test-hall Proctoring & Access ControlProject | Unified Operations Centre for Centres & PlatformsProject | Data | 2027-06-30 | 60 days | 45 days | — | At risk | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@sca.sa |
DEP-028 Civil Defence safety certificate | General Directorate of Civil DefenceExternal entity | Branch systems commissioning (HVAC & fire)Task | Approval | 2026-12-31 | 0 days | 0 days | — | On track | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@sca.sa |