Saudi Contractors AuthorityMunjaz11My actionsNotifications

CP-2026-02Version ⁦1⁩

Al-Khobar Branch — Rehabilitation & Extension

Approved — under wayCriticalOverdue: ⁦1⁩

One corrective plan: why the project slipped, the rule that triggered it, the actions, the days won back, approval and follow-up.

What triggered the plan

The project’s reading the day the rule fired, and today.

Detected on ⁦2026-09-01⁩

Slip past the baseline

At detection
104 days
Today
126 days
Limit
> 40

Schedule performance index

At detection
0.76
Today
0.74
Limit
< 0.85

A rule approved by the Project Approval Committee (PMO-2026/14), read automatically from the project’s data.

Days won back

The forecast finish without the plan, with it, and the difference.

  1. Baseline

    2026-09-30
  2. Without the plan

    2027-03-20

    +171 days

  3. With the plan

    2027-02-03

    +126 days

Wins back 45 days

Achieved so far: 0 days

Why it slipped

The main contractor’s cash-flow distress and unpaid subcontractors, the underground tanks failing the tightness test, and training & test hall wing changes never shown to Civil Defence

Corrective actions

Each action with its owner, date, status and the days it wins back; overdue ones are shaded.

⁦1⁩ of ⁦5⁩ done
  • An executive task force on the contractor’s distress

    Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.sa
    Done⁦2026-09-22⁩2026-09-2211 Rabiʻ II 1448 AH
  • Appoint an independent financial adviser to audit contractor liquidity

    Khalid N. Al-MutairiKhalid N. Al-MutairiSenior Finance & Procurement SpecialistP-007k.almutairi@sca.saACT-0307
    Overdue8 days overdue2026-10-209 Jumada I 1448 AHWins back 10 days
  • Pay subcontractors directly from the next certificate

    Khalid N. Al-MutairiKhalid N. Al-MutairiSenior Finance & Procurement SpecialistP-007k.almutairi@sca.saACT-0308
    Not startedIn 8 days2026-11-0525 Jumada I 1448 AHWins back 20 days
  • Re-run the tanks’ tightness test after repair

    Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@sca.saACT-0309
    In progressIn 5 days2026-11-0222 Jumada I 1448 AHWins back 5 days
  • An early review of the fire and evacuation drawings with Civil Defence

    Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@sca.sa
    In progressIn 18 days2026-11-155 Jumada II 1448 AHWins back 10 days

Follow-up

The project’s readings after the plan was approved, with the PMO’s notes.

  1. 2026-10-27Dr. Noura M. Al-Otaibi126 days lateSPI ⁦0.74⁩

    Labour stopped for four days; direct payment raised to the Executive Committee (ESC-2026-021)

  2. 2026-10-13Karim Haddad118 days lateSPI ⁦0.75⁩

    The financial adviser is still not appointed (conflict of interest); re-tendering

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close