Contractor financial audit — Al-Khobar branch
Al-Khobar Branch — Rehabilitation & Extension
1. Executive summary
This report gives the position of Al-Khobar Branch — Rehabilitation & Extension to date: 68% complete against 92% planned, SPI 0.74, CPI 0.84, and an estimate at completion of SAR 490.5M.
- Project
- Al-Khobar Branch — Rehabilitation & Extension (PRJ-2026-004)
- Project manager
- Eng. Waleed O. Al-Juhani
- Budget
- SAR 412.0M
- Progress
- 68% actual against 92% planned
- Forecast finish
- 2027-02-03
2. Key findings
- All planned milestones of the period met except one deferred
- Actual spend rose in line with the work done
- Three high risks under treatment, each with a named owner
3. Recommendations & decisions needed
- Approve the proposed treatment of the high risks
- Track the open findings with the vendor weekly
Prepared by
Khalid N. Al-Mutairi
Project manager