Subject: Default notice and request for a corrective plan
United Buildings & Operations Co.
Greetings,
With reference to contract SCA/2024/003, progress has fallen to 68% against 92% planned and the supply of the new wing’s central air-conditioning units has stopped. This letter is formal notice of default under the contract.
Submit a corrective plan approved by your senior management within fourteen days, failing which the Authority will act as the law allows, including withdrawing the work.
With our kind regards,
Secretary-General
Dr. Abdullah S. Al-Qahtani